IAC Assessment: DS0173
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: DS0173
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center South Dakota State
Assessment Year 2000
Principal Product Pillows
NAICS n/a
SIC 2392 - Housefurnishings, Nec
Sales $5,000,000-$10,000,000
# of Employees 89
Plant Area (Sq.Ft.) 58,200
Annual Production 750,000 Pieces
Production Hrs. Annual 2,210
Location (State) SD
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $22,419 662,661 kWh $0.03
Electricity Demand $18,894 2,664 kW-months/year $7.09
Electricity Fees $3,434 - $ -
Natural Gas $4,510 792 MMBtu $5.69
TOTAL ENERGY COSTS $58,617
RECOMMENDED SAVINGS* $18,046 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $4,231
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) Administrative Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) Administrative Changes
$ kWh $ kW-months/year $ $ $ MMBtu $ lb $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,510
Cost:
$3,702
$709 20,809 $801 113 - - - - - - - - $709
20,809
kWh
$801
113
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
-
-
$
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$588
Cost:
$700
- - - - $588 - - - - - - - -
-
kWh
-
-
kW-months/year
$588
-
$
-
-
MMBtu
-
-
lb
-
-
$
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$1,399
Cost:
$1,595
- - - - - - $1,399 246 - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$1,399
246
MMBtu
-
-
lb
-
-
$
04: 2.7122 DISCONNECT BALLASTS Savings:
$734
Cost:
$160
$342 9,965 $392 55 - - - - - - - - $342
9,965
kWh
$392
55
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
-
-
$
05: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$5,574
Cost:
$8,370
- - - - - - - - $5,574 24,000 - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$5,574
24,000
lb
-
-
$
06: 3.6125 SELL COMBUSTIBLE WASTE Savings:
$2,721
Cost:
$8,050
- - - - - - - - $2,721 44,000 - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$2,721
44,000
lb
-
-
$
07: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES Savings:
$5,520
Cost:
-
- - - - - - - - - - $5,520 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
$5,520
-
$
TOTAL RECOMMENDED Savings:
$18,046
Cost:
$22,577
$1,051 30,774 $1,193 168 $588 - $1,399 246 $8,295 68,000 $5,520 - $1,051
30,774
kWh
$1,193
168
kW-months/year
$588
-
$
$1,399
246
MMBtu
$8,295
68,000
lb
$5,520
-
$
TOTAL IMPLEMENTED Savings:
$4,231
Cost:
$6,157
$1,051 30,774 $1,193 168 $588 - $1,399 246 - - - - $1,051
30,774
kWh
$1,193
168
kW-months/year
$588
-
$
$1,399
246
MMBtu
-
-
lb
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ lb $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) Administrative Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) Administrative Changes