Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1982 |
Principal Product | THERMOFORMED PLASTIC |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 400 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 1,550,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $847,982 | 25,145,956 | kWh | $0.03 |
Natural Gas | $33,564 | 9,424 | MMBtu | $3.56 |
TOTAL ENERGY COSTS | $881,546 | |||
RECOMMENDED SAVINGS* | $28,846 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $28,846 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Usage | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,021 Cost: $400 |
$2,021 | 60,082 |
$2,021 60,082 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $9,712 Cost: - |
$9,712 | 288,101 |
$9,712 288,101 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2694 USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE |
Savings: $1,841 Cost: - |
$1,841 | 54,513 |
$1,841 54,513 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $15,272 Cost: $150 |
$15,272 | 452,814 |
$15,272 452,814 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $28,846 Cost: $550 |
$28,846 | 855,510 | $28,846 855,510 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $28,846 Cost: $550 |
$28,846 | 855,510 | $28,846 855,510 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Usage |