Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1985 |
Principal Product | SODIUM SILICATE |
NAICS | n/a |
SIC | 2819 - Industrial Inorganic Chemicals, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 25 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 130,000 Pounds |
Production Hrs. Annual | 7,728 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $313,001 | 6,953,986 | kWh | $0.05 |
Natural Gas | $787,630 | 184,000 | MMBtu | $4.28 |
TOTAL ENERGY COSTS | $1,100,631 | |||
RECOMMENDED SAVINGS* | $59,476 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $59,476 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $944 Cost: $617 |
$944 | 21,102 | - | - |
$944 21,102 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $732 Cost: $230 |
$732 | 16,120 | - | - |
$732 16,120 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $18,500 Cost: $75,000 |
- | - | $18,500 | 4,440 |
- - kWh |
$18,500 4,440 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2444 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS |
Savings: $39,300 Cost: $25,000 |
- | - | $39,300 | 9,430 |
- - kWh |
$39,300 9,430 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $59,476 Cost: $100,847 |
$1,676 | 37,222 | $57,800 | 13,870 | $1,676 37,222 kWh |
$57,800 13,870 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $59,476 Cost: $100,847 |
$1,676 | 37,222 | $57,800 | 13,870 | $1,676 37,222 kWh |
$57,800 13,870 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |