Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1996 |
Principal Product | Porous Plastics |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 175,000 |
Annual Production | 11,000,000 Pounds |
Production Hrs. Annual | 6,864 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $147,149 | 5,573,271 | kWh | $0.03 |
Electricity Demand | $116,568 | 13,614 | kW-months/year | $8.56 |
Electricity Fees | $39,058 | - | $ | - |
Natural Gas | $119,680 | 39,251 | MMBtu | $3.05 |
Fuel Oil #2 | $14,743 | 2,715 | MMBtu | $5.43 |
TOTAL ENERGY COSTS | $439,648 | |||
RECOMMENDED SAVINGS* | $125,911 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,484 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $406 Cost: $2,115 |
$229 | 8,792 | $154 | 15 | $23 | - | - | - | - | - | - | - | - | - |
$229 8,792 kWh |
$154 15 kW-months/year |
$23 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $761 Cost: $720 |
$430 | 16,413 | $280 | 28 | $51 | - | - | - | - | - | - | - | - | - |
$430 16,413 kWh |
$280 28 kW-months/year |
$51 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $10,317 Cost: $1,450 |
$5,829 | 220,692 | $2,884 | 384 | $1,604 | - | - | - | - | - | - | - | - | - |
$5,829 220,692 kWh |
$2,884 384 kW-months/year |
$1,604 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $21,562 Cost: $1,890 |
$12,182 | 461,313 | $8,132 | 804 | $1,248 | - | - | - | - | - | - | - | - | - |
$12,182 461,313 kWh |
$8,132 804 kW-months/year |
$1,248 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $7,890 Cost: $6,400 |
- | - | - | - | - | - | $7,890 | 2,588 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$7,890 2,588 MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $84,975 Cost: $3,860 |
- | - | - | - | - | - | - | - | $1,225 | 87,500 | $(-3,750) | - | $87,500 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$1,225 87,500 lb |
$(-3,750) - $ |
$87,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $125,911 Cost: $16,435 |
$18,670 | 707,210 | $11,450 | 1,231 | $2,926 | - | $7,890 | 2,588 | $1,225 | 87,500 | $(-3,750) | - | $87,500 | - | $18,670 707,210 kWh |
$11,450 1,231 kW-months/year |
$2,926 - $ |
$7,890 2,588 MMBtu |
$1,225 87,500 lb |
$(-3,750) - $ |
$87,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,484 Cost: $4,285 |
$6,488 | 245,897 | $3,318 | 427 | $1,678 | - | - | - | - | - | - | - | - | - | $6,488 245,897 kWh |
$3,318 427 kW-months/year |
$1,678 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material |