Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1996 |
Principal Product | Printed Wood Grain Paper |
NAICS | n/a |
SIC | 2671 - Paper Coated & Laminated, Packaging |
Sales | $50,000,000-$100,000,000 |
# of Employees | 140 |
Plant Area (Sq.Ft.) | 200,000 |
Annual Production | 823,000 Thousand Feet |
Production Hrs. Annual | 8,424 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $262,592 | 10,674,385 | kWh | $0.02 |
Electricity Demand | $303,875 | 25,344 | kW-months/year | $11.99 |
Electricity Fees | $51,831 | - | $ | - |
Natural Gas | $385,330 | 99,436 | MMBtu | $3.88 |
Fuel Oil #2 | $39,702 | 8,350 | MMBtu | $4.75 |
TOTAL ENERGY COSTS | $1,176,712 | |||
RECOMMENDED SAVINGS* | $129,554 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2612 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION |
Savings: $9,934 Cost: $5,000 |
$9,520 | 337,046 | - | - | $414 | - | - | - | - | - | - | - |
$9,520 337,046 kWh |
- - kW-months/year |
$414 - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1212 OPERATE BOILERS ON HIGH FIRE SETTING |
Savings: $8,380 Cost: $2,000 |
- | - | - | - | - | - | $8,380 | 2,165 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$8,380 2,165 MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.4151 MINIMIZE WATER USAGE |
Savings: $62,640 Cost: - |
- | - | - | - | - | - | - | - | $31,320 | 12,000,000 | $31,320 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$31,320 12,000,000 Tgal |
$31,320 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT |
Savings: $9,570 Cost: $75,450 |
$9,114 | 370,457 | - | - | $456 | - | - | - | - | - | - | - |
$9,114 370,457 kWh |
- - kW-months/year |
$456 - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4225 INSTALL COMMON HEADER ON COMPRESSORS |
Savings: $29,270 Cost: $96,000 |
$17,030 | 692,263 | $10,846 | 904 | $1,394 | - | - | - | - | - | - | - |
$17,030 692,263 kWh |
$10,846 904 kW-months/year |
$1,394 - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $9,760 Cost: $48,450 |
$5,454 | 221,571 | $3,844 | 321 | $462 | - | - | - | - | - | - | - |
$5,454 221,571 kWh |
$3,844 321 kW-months/year |
$462 - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $129,554 Cost: $226,900 |
$41,118 | 1,621,337 | $14,690 | 1,225 | $2,726 | - | $8,380 | 2,165 | $31,320 | 12,000,000 | $31,320 | - | $41,118 1,621,337 kWh |
$14,690 1,225 kW-months/year |
$2,726 - $ |
$8,380 2,165 MMBtu |
$31,320 12,000,000 Tgal |
$31,320 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Ancillary Material Cost |