IAC Assessment: GT0616
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: GT0616
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Georgia Institute of Technology
Assessment Year 1997
Principal Product Computer Monitors
NAICS n/a
SIC 3575 - Computer Terminals
Sales $10,000,000-$50,000,000
# of Employees 165
Plant Area (Sq.Ft.) 70,000
Annual Production 13,200 Pieces
Production Hrs. Annual 2,500
Location (State) GA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $34,792 1,303,048 kWh $0.03
Electricity Demand $73,881 4,932 kW-months/year $14.98
Electricity Fees $6,520 - $ -
Natural Gas $9,478 1,333 MMBtu $7.11
TOTAL ENERGY COSTS $135,751
RECOMMENDED SAVINGS* $35,339 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $14,179
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ lb $ $ $ $
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$21,160
Cost:
-
- - - - - - - - - - $21,160 - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
$21,160
-
$
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$8,600
Cost:
$18,500
$2,056 77,081 $6,157 411 $387 - - - - - - - - - $2,056
77,081
kWh
$6,157
411
kW-months/year
$387
-
$
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
03: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$2,385
Cost:
-
$98 3,810 $1,665 120 - - $622 88 - - - - - - $98
3,810
kWh
$1,665
120
kW-months/year
-
-
$
$622
88
MMBtu
-
-
lb
-
-
$
-
-
$
04: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$2,964
Cost:
$6,700
- - - - - - - - - - - - $2,964 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
lb
-
-
$
$2,964
-
$
05: 3.5311 RECOVER AND REUSE WASTE MATERIAL Savings:
$230
Cost:
-
- - - - - - - - $230 7,200 - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$230
7,200
lb
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$35,339
Cost:
$25,200
$2,154 80,891 $7,822 531 $387 - $622 88 $230 7,200 $21,160 - $2,964 - $2,154
80,891
kWh
$7,822
531
kW-months/year
$387
-
$
$622
88
MMBtu
$230
7,200
lb
$21,160
-
$
$2,964
-
$
TOTAL IMPLEMENTED Savings:
$14,179
Cost:
$25,200
$2,154 80,891 $7,822 531 $387 - $622 88 $230 7,200 - - $2,964 - $2,154
80,891
kWh
$7,822
531
kW-months/year
$387
-
$
$622
88
MMBtu
$230
7,200
lb
-
-
$
$2,964
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ lb $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Natural Gas Solid Waste (non-haz) Administrative Changes Ancillary Material Cost