IAC Assessment: GT0645
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: GT0645
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Georgia Institute of Technology
Assessment Year 1998
Principal Product Bathroom Rugs
NAICS n/a
SIC 2273 - Carpets And Rugs
Sales $5,000,000-$10,000,000
# of Employees 170
Plant Area (Sq.Ft.) 80,000
Annual Production 1,500,000 Pieces
Production Hrs. Annual 6,000
Location (State) GA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $64,020 2,712,778 kWh $0.02
Electricity Demand $100,080 7,113 kW-months/year $14.07
Electricity Fees $22,183 - $ -
Natural Gas $267,471 64,629 MMBtu $4.14
TOTAL ENERGY COSTS $548,788
RECOMMENDED SAVINGS* $88,668 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $56,731
#|Description Savings
Cost
Status Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Ancillary Material Cost Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Ancillary Material Cost
$ kW-months/year $ MMBtu $ Tgal $ lb $ $ $ $
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$20,559
Cost:
$10,000
$18,380 98 - - - - - - - - $2,179 - $18,380
98
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
$
$2,179
-
$
02: 2.2212 USE MINIMUM SAFE OVEN VENTILATION Savings:
$2,720
Cost:
-
- - $2,720 135 - - - - - - - - -
-
kW-months/year
$2,720
135
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,810
Cost:
$7,000
- - $1,810 463 - - - - - - - - -
-
kW-months/year
$1,810
463
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
04: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$34,362
Cost:
$22,000
- - $34,362 8,300 - - - - - - - - -
-
kW-months/year
$34,362
8,300
MMBtu
-
-
Tgal
-
-
lb
-
-
$
-
-
$
05: 4.213 PURCHASE MATERIAL FROM SUPPLIER IN CUSTOMIZED PACKAGING Savings:
$3,970
Cost:
-
- - - - - - $1,470 98,000 $2,500 - - - -
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$1,470
98,000
lb
$2,500
-
$
-
-
$
06: 3.4113 TREAT AND REUSE RINSE WATERS Savings:
$25,247
Cost:
$30,000
- - - - $13,336 7,826,200 - - - - $11,911 - -
-
kW-months/year
-
-
MMBtu
$13,336
7,826,200
Tgal
-
-
lb
-
-
$
$11,911
-
$
TOTAL RECOMMENDED Savings:
$88,668
Cost:
$69,000
$18,380 98 $38,892 8,898 $13,336 7,826,200 $1,470 98,000 $2,500 - $14,090 - $18,380
98
kW-months/year
$38,892
8,898
MMBtu
$13,336
7,826,200
Tgal
$1,470
98,000
lb
$2,500
-
$
$14,090
-
$
TOTAL IMPLEMENTED Savings:
$56,731
Cost:
$39,000
$18,380 98 $36,172 8,763 - - - - - - $2,179 - $18,380
98
kW-months/year
$36,172
8,763
MMBtu
-
-
Tgal
-
-
lb
-
-
$
$2,179
-
$
Savings
Cost
$ kW-months/year $ MMBtu $ Tgal $ lb $ $ $ $
Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Ancillary Material Cost Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Personnel Changes Ancillary Material Cost