Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1998 |
Principal Product | Industrial Belts |
NAICS | n/a |
SIC | 3052 - Rubber & Plastics Hose & Belting |
Sales | $1,000,000-$5,000,000 |
# of Employees | 34 |
Plant Area (Sq.Ft.) | 10,500 |
Annual Production | 60,000 Pounds |
Production Hrs. Annual | 2,000 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $22,535 | 201,348 | kWh | $0.11 |
Natural Gas | $4,242 | 662 | MMBtu | $6.41 |
TOTAL ENERGY COSTS | $27,970 | |||
RECOMMENDED SAVINGS* | $10,829 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $9,500 |
#|Description |
Savings Cost |
Status | Electricity Usage | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Solid Waste (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,034 Cost: $4,875 |
$1,034 | 11,430 | - | - | - | - |
$1,034 11,430 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $153 Cost: $168 |
$153 | 1,758 | - | - | - | - |
$153 1,758 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $97 Cost: $52 |
$97 | 1,172 | - | - | - | - |
$97 1,172 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $7,500 Cost: - |
- | - | - | - | $7,500 | - |
- - kWh |
- - lb |
$7,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $2,000 Cost: $1,000 |
- | - | - | - | $2,000 | - |
- - kWh |
- - lb |
$2,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5218 REUSE / RECYCLE/ SELL RUBBER PRODUCTS |
Savings: $45 Cost: - |
- | - | $45 | 3,000 | - | - |
- - kWh |
$45 3,000 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $10,829 Cost: $6,095 |
$1,284 | 14,360 | $45 | 3,000 | $9,500 | - | $1,284 14,360 kWh |
$45 3,000 lb |
$9,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $9,500 Cost: $1,000 |
- | - | - | - | $9,500 | - | - - kWh |
- - lb |
$9,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Solid Waste (non-haz) | Personnel Changes |