Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1999 |
Principal Product | carpet |
NAICS | n/a |
SIC | 2269 - Finishing Plants, Nec |
Sales | $1,000,000-$5,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 160,000 |
Annual Production | 7,000,000 Pounds |
Production Hrs. Annual | 7,200 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $27,448 | 1,332,943 | kWh | $0.02 |
Electricity Demand | $24,946 | 5,177 | kW-months/year | $4.82 |
Electricity Fees | $3,138 | - | $ | - |
Natural Gas | $10,122 | 1,891 | MMBtu | $5.35 |
TOTAL ENERGY COSTS | $80,551 | |||
RECOMMENDED SAVINGS* | $75,910 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,454 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $122 Cost: $350 |
$115 | 3,810 | - | - | $7 | - | - | - | - | - |
$115 3,810 kWh |
- - kW-months/year |
$7 - $ |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $162 Cost: $50 |
$153 | 5,862 | - | - | $9 | - | - | - | - | - |
$153 5,862 kWh |
- - kW-months/year |
$9 - $ |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2531 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR |
Savings: $182 Cost: - |
$172 | 6,448 | - | - | $10 | - | - | - | - | - |
$172 6,448 kWh |
- - kW-months/year |
$10 - $ |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE |
Savings: $62 Cost: $200 |
$58 | 2,345 | - | - | $4 | - | - | - | - | - |
$58 2,345 kWh |
- - kW-months/year |
$4 - $ |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,292 Cost: $18,568 |
$4,554 | 174,971 | $1,382 | 24 | $356 | - | - | - | - | - |
$4,554 174,971 kWh |
$1,382 24 kW-months/year |
$356 - $ |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.423 MOVE PRODUCT USING MECHANICAL MEANS |
Savings: $52,560 Cost: $8,050 |
- | - | - | - | - | - | - | - | $52,560 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - lb |
$52,560 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $1,740 Cost: $1,719 |
- | - | - | - | - | - | - | - | $1,740 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - lb |
$1,740 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE |
Savings: $14,790 Cost: - |
- | - | - | - | - | - | $14,790 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$14,790 - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $75,910 Cost: $28,937 |
$5,052 | 193,436 | $1,382 | 24 | $386 | - | $14,790 | - | $54,300 | - | $5,052 193,436 kWh |
$1,382 24 kW-months/year |
$386 - $ |
$14,790 - lb |
$54,300 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,454 Cost: $18,618 |
$4,707 | 180,833 | $1,382 | 24 | $365 | - | - | - | - | - | $4,707 180,833 kWh |
$1,382 24 kW-months/year |
$365 - $ |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (non-haz) | Personnel Changes |