Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 2000 |
Principal Product | Wooden Furniture |
NAICS | n/a |
SIC | 2426 - Hardwood Dimension & Flooring Mills |
Sales | $5,000,000-$10,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 58,000 |
Annual Production | 109,665 Pieces |
Production Hrs. Annual | 2,000 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $33,613 | 390,844 | kWh | $0.09 |
Electricity Fees | $5,246 | - | $ | - |
Natural Gas | $2,884 | 440 | MMBtu | $6.55 |
LPG | $3,138 | 404 | MMBtu | $7.77 |
TOTAL ENERGY COSTS | $46,483 | |||
RECOMMENDED SAVINGS* | $29,432 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Natural Gas | Primary Raw Material | Primary Product | Electricity Usage | Electricity Fees | Natural Gas | Primary Raw Material | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $878 Cost: $635 |
$(-87) | (-1,017) | $(-4) | - | $969 | 148 | - | - | - | - |
$(-87) (-1,017) kWh |
$(-4) - $ |
$969 148 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4223 INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM |
Savings: $1,244 Cost: $525 |
$1,185 | 13,775 | $59 | - | - | - | - | - | - | - |
$1,185 13,775 kWh |
$59 - $ |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7145 INSTALL SKYLIGHTS |
Savings: $1,332 Cost: $4,380 |
$1,269 | 14,760 | $63 | - | - | - | - | - | - | - |
$1,269 14,760 kWh |
$63 - $ |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $499 Cost: - |
$475 | 5,524 | $24 | - | - | - | - | - | - | - |
$475 5,524 kWh |
$24 - $ |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.8121 COVER CONTAINERS TO MINIMIZE EVAPORATIVE LOSSES |
Savings: $20,979 Cost: $900 |
- | - | - | - | - | - | $20,979 | - | - | - |
- - kWh |
- - $ |
- - MMBtu |
$20,979 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.625 DEVELOP STANDARD OPERATING PROCEDURES |
Savings: $4,500 Cost: $20,700 |
- | - | - | - | - | - | - | - | $4,500 | - |
- - kWh |
- - $ |
- - MMBtu |
- - $ |
$4,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $29,432 Cost: $27,140 |
$2,842 | 33,042 | $142 | - | $969 | 148 | $20,979 | - | $4,500 | - | $2,842 33,042 kWh |
$142 - $ |
$969 148 MMBtu |
$20,979 - $ |
$4,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - $ |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Natural Gas | Primary Raw Material | Primary Product | Electricity Usage | Electricity Fees | Natural Gas | Primary Raw Material | Primary Product |