Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 2000 |
Principal Product | Plastic Gears |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 40 |
Plant Area (Sq.Ft.) | 40,000 |
Annual Production | 5,000,000 Pounds |
Production Hrs. Annual | 8,500 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $184,260 | 4,945,194 | kWh | $0.04 |
Natural Gas | $651 | 88 | MMBtu | $7.40 |
TOTAL ENERGY COSTS | $186,689 | |||
RECOMMENDED SAVINGS* | $113,129 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $21,857 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Primary Raw Material | Electricity Usage | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $7,357 Cost: $2,000 |
$2,557 | 52,462 | - | - | - | - | $4,800 | - | - | - | - | - |
$2,557 52,462 kWh |
- - MMBtu |
- - Tgal |
$4,800 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT |
Savings: $7,810 Cost: $1,000 |
$7,810 | 330,305 | - | - | - | - | - | - | - | - | - | - |
$7,810 330,305 kWh |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $6,690 Cost: $4,000 |
$6,690 | 204,865 | - | - | - | - | - | - | - | - | - | - |
$6,690 204,865 kWh |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) |
Savings: $3,465 Cost: $500 |
- | - | - | - | $3,465 | 480,000 | - | - | - | - | - | - |
- - kWh |
- - MMBtu |
$3,465 480,000 Tgal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $53,500 Cost: $170,000 |
$44,500 | 1,199,590 | - | - | - | - | - | - | - | - | $9,000 | - |
$44,500 1,199,590 kWh |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
$9,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3192 USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS |
Savings: $9,831 Cost: $26,400 |
$14,927 | 54,220 | $(-5,096) | (-690) | - | - | - | - | - | - | - | - |
$14,927 54,220 kWh |
$(-5,096) (-690) MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $19,321 Cost: $41,750 |
$19,321 | 429,953 | - | - | - | - | - | - | - | - | - | - |
$19,321 429,953 kWh |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $5,155 Cost: - |
- | - | - | - | - | - | - | - | $5,155 | - | - | - |
- - kWh |
- - MMBtu |
- - Tgal |
- - $ |
$5,155 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $113,129 Cost: $245,650 |
$95,805 | 2,271,395 | $(-5,096) | (-690) | $3,465 | 480,000 | $4,800 | - | $5,155 | - | $9,000 | - | $95,805 2,271,395 kWh |
$(-5,096) (-690) MMBtu |
$3,465 480,000 Tgal |
$4,800 - $ |
$5,155 - $ |
$9,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $21,857 Cost: $7,000 |
$17,057 | 587,632 | - | - | - | - | $4,800 | - | - | - | - | - | $17,057 587,632 kWh |
- - MMBtu |
- - Tgal |
$4,800 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Primary Raw Material | Electricity Usage | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Primary Raw Material |