Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 2003 |
Principal Product | COTTON YARN |
NAICS | 313110 - Fiber, Yarn, and Thread Mills |
SIC | 2281 - Yarn Spinning Mills |
Sales | $10,000,000-$50,000,000 |
# of Employees | 115 |
Plant Area (Sq.Ft.) | 198,000 |
Annual Production | 48,400,000 Pounds |
Production Hrs. Annual | 8,400 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $826,270 | 26,673,163 | kWh | $0.03 |
TOTAL ENERGY COSTS | $838,418 | |||
RECOMMENDED SAVINGS* | $42,185 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $23,674 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $732 Cost: $450 |
$732 | 22,219 | - | - | - | - | - | - |
$732 22,219 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $12,742 Cost: - |
$6,505 | 197,392 | $6,237 | 282 | - | - | - | - |
$6,505 197,392 kWh |
$6,237 282 kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $2,064 Cost: $948 |
$2,064 | 62,600 | - | - | - | - | - | - |
$2,064 62,600 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $830 Cost: $773 |
$830 | 25,179 | - | - | - | - | - | - |
$830 25,179 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.4155 METER WASTE WATER |
Savings: $8,405 Cost: $1,932 |
- | - | - | - | $8,405 | 625,238 | - | - |
- - kWh |
- - kW-months/year |
$8,405 625,238 Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $3,944 Cost: $3,598 |
$3,944 | 119,671 | - | - | - | - | - | - |
$3,944 119,671 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $164 Cost: $1,068 |
$164 | 4,967 | - | - | - | - | - | - |
$164 4,967 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $10,106 Cost: $20,000 |
$10,106 | 306,600 | - | - | - | - | - | - |
$10,106 306,600 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.8123 PAY UTILITY BILLS ON TIME |
Savings: $3,198 Cost: - |
- | - | - | - | - | - | $3,198 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$3,198 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $42,185 Cost: $28,769 |
$24,345 | 738,628 | $6,237 | 282 | $8,405 | 625,238 | $3,198 | - | $24,345 738,628 kWh |
$6,237 282 kW-months/year |
$8,405 625,238 Tgal |
$3,198 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $23,674 Cost: $6,837 |
$14,239 | 432,028 | $6,237 | 282 | - | - | $3,198 | - | $14,239 432,028 kWh |
$6,237 282 kW-months/year |
- - Tgal |
$3,198 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes |