Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 2007 |
Principal Product | Jail Modules |
NAICS | 327390 - Other Concrete Product Manufacturing |
SIC | 3272 - Concrete Products, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 343 |
Plant Area (Sq.Ft.) | 127,000 |
Annual Production | 1,250 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $130,742 | 2,867,140 | kWh | $0.05 |
Electricity Demand | $90,596 | 5,925 | kW-months/year | $15.29 |
Electricity Fees | $1,053 | - | $ | - |
Natural Gas | $464,736 | 55,034 | MMBtu | $8.44 |
TOTAL ENERGY COSTS | $687,127 | |||
RECOMMENDED SAVINGS* | $132,390 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $102,272 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $4,990 Cost: - |
$4,990 | 109,400 | - | - | - | - | - | - | - | - |
$4,990 109,400 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $18,300 Cost: $3,250 |
$18,300 | 401,968 | - | - | - | - | - | - | - | - |
$18,300 401,968 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $14,528 Cost: $1,800 |
- | - | - | - | $13,961 | 1,655 | $567 | 138,292 | - | - |
- - kWh |
- - kW-months/year |
$13,961 1,655 MMBtu |
$567 138,292 Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $47,920 Cost: - |
- | - | - | - | $47,920 | 5,796 | - | - | - | - |
- - kWh |
- - kW-months/year |
$47,920 5,796 MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $13,963 Cost: - |
- | - | - | - | - | - | - | - | $13,963 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$13,963 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,571 Cost: $7,090 |
$1,764 | 38,660 | $807 | 53 | - | - | - | - | - | - |
$1,764 38,660 kWh |
$807 53 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $30,118 Cost: $41,616 |
$21,586 | 472,968 | $8,532 | 558 | - | - | - | - | - | - |
$21,586 472,968 kWh |
$8,532 558 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $132,390 Cost: $53,756 |
$46,640 | 1,022,996 | $9,339 | 611 | $61,881 | 7,451 | $567 | 138,292 | $13,963 | - | $46,640 1,022,996 kWh |
$9,339 611 kW-months/year |
$61,881 7,451 MMBtu |
$567 138,292 Tgal |
$13,963 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $102,272 Cost: $12,140 |
$25,054 | 550,028 | $807 | 53 | $61,881 | 7,451 | $567 | 138,292 | $13,963 | - | $25,054 550,028 kWh |
$807 53 kW-months/year |
$61,881 7,451 MMBtu |
$567 138,292 Tgal |
$13,963 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Administrative Changes |