Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 2008 |
Principal Product | Gear Pumps |
NAICS | 333911 - Pump and Pumping Equipment Manufacturing |
SIC | 3561 - Pumps And Pumping Equipment |
Sales | $10,000,000-$50,000,000 |
# of Employees | 215 |
Plant Area (Sq.Ft.) | 156,040 |
Annual Production | 32,400 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $375,113 | 7,964,179 | kWh | $0.05 |
Electricity Demand | $213,636 | 17,132 | kW-months/year | $12.47 |
Electricity Fees | $47,190 | - | $ | - |
Natural Gas | $131,134 | 9,180 | MMBtu | $14.28 |
TOTAL ENERGY COSTS | $767,073 | |||
RECOMMENDED SAVINGS* | $127,768 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $54,768 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $24,327 Cost: $3,500 |
$17,892 | 380,680 | $6,435 | 516 | - | - |
$17,892 380,680 kWh |
$6,435 516 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $4,774 Cost: - |
$3,502 | 74,500 | $1,272 | 102 | - | - |
$3,502 74,500 kWh |
$1,272 102 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER |
Savings: $9,073 Cost: $9,000 |
- | - | - | - | $9,073 | 643 |
- - kWh |
- - kW-months/year |
$9,073 643 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $790 Cost: $2,775 |
- | - | - | - | $790 | 56 |
- - kWh |
- - kW-months/year |
$790 56 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT |
Savings: $9,500 Cost: $15,600 |
$9,500 | 202,167 | - | - | - | - |
$9,500 202,167 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2314 REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT |
Savings: $22,600 Cost: $60,000 |
- | - | - | - | $22,600 | 1,602 |
- - kWh |
- - kW-months/year |
$22,600 1,602 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $25,667 Cost: $37,500 |
$20,639 | 438,190 | $5,028 | 403 | - | - |
$20,639 438,190 kWh |
$5,028 403 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $31,037 Cost: $64,132 |
$20,578 | 437,835 | $10,459 | 839 | - | - |
$20,578 437,835 kWh |
$10,459 839 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $127,768 Cost: $192,507 |
$72,111 | 1,533,372 | $23,194 | 1,860 | $32,463 | 2,301 | $72,111 1,533,372 kWh |
$23,194 1,860 kW-months/year |
$32,463 2,301 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $54,768 Cost: $41,000 |
$42,033 | 893,370 | $12,735 | 1,021 | - | - | $42,033 893,370 kWh |
$12,735 1,021 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |