Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 2010 |
Principal Product | Prepared Frozen Foods |
NAICS | 311411 - Frozen Fruit, Juice, and Vegetable Manufacturing |
SIC | 2038 - Frozen Specialties, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 290 |
Plant Area (Sq.Ft.) | 20,800 |
Annual Production | 12,000,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $293,202 | 6,448,615 | kWh | $0.05 |
Electricity Demand | $189,307 | 13,920 | kW-months/year | $13.60 |
Natural Gas | $115,317 | 18,157 | MMBtu | $6.35 |
TOTAL ENERGY COSTS | $597,826 | |||
RECOMMENDED SAVINGS* | $127,739 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $83,873 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $960 Cost: $1,300 |
$960 | 20,135 | - | - | - | - |
$960 20,135 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $9,230 Cost: - |
$9,230 | 193,920 | - | - | - | - |
$9,230 193,920 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,954 Cost: $19,633 |
$2,628 | 49,410 | $2,326 | 141 | - | - |
$2,628 49,410 kWh |
$2,326 141 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $487 Cost: $150,000 |
$487 | 10,230 | - | - | - | - |
$487 10,230 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $9,328 Cost: $20,000 |
$6,510 | 121,660 | $2,818 | 170 | - | - |
$6,510 121,660 kWh |
$2,818 170 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $26,710 Cost: $73,600 |
$26,710 | 561,139 | - | - | - | - |
$26,710 561,139 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $12,202 Cost: $20,000 |
$8,510 | 159,030 | $3,692 | 223 | - | - |
$8,510 159,030 kWh |
$3,692 223 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.5113 USE DIRECT FLAME IMPINGEMENT OR INFRARED PROCESSING FOR CHAMBER TYPE HEATING |
Savings: $63,868 Cost: $350,000 |
- | - | - | - | $63,868 | 10,058 |
- - kWh |
- - kW-months/year |
$63,868 10,058 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $127,739 Cost: $634,533 |
$55,035 | 1,115,524 | $8,836 | 534 | $63,868 | 10,058 | $55,035 1,115,524 kWh |
$8,836 534 kW-months/year |
$63,868 10,058 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $83,873 Cost: $521,300 |
$17,187 | 345,945 | $2,818 | 170 | $63,868 | 10,058 | $17,187 345,945 kWh |
$2,818 170 kW-months/year |
$63,868 10,058 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |