Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 2017 |
Principal Product | Gypsum products |
NAICS | 327420 - Gypsum Product Manufacturing |
SIC | 3275 - Gypsum Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 33 |
Plant Area (Sq.Ft.) | 50,000 |
Annual Production | 186,500 Units |
Production Hrs. Annual | 4,250 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $119,943 | 1,015,260 | kWh | $0.12 |
Natural Gas | $8,079 | 366 | MMBtu | $22.10 |
TOTAL ENERGY COSTS | $128,022 | |||
RECOMMENDED SAVINGS* | $95,582 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $47,255 |
#|Description |
Savings Cost |
Status | Electricity Usage | Administrative Changes | Electricity Usage | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,203 Cost: $150 |
$1,203 | 10,029 | - | - |
$1,203 10,029 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.4155 METER WASTE WATER |
Savings: $38,607 Cost: $18,000 |
- | - | $38,607 | - |
- - kWh |
$38,607 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $8,648 Cost: $9,390 |
$8,648 | 72,055 | - | - |
$8,648 72,055 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $4,223 Cost: $8,011 |
$4,223 | 35,794 | - | - |
$4,223 35,794 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.9113 USE SOLAR HEAT FOR HEAT |
Savings: $42,901 Cost: $150,153 |
$42,901 | 363,578 | - | - |
$42,901 363,578 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $95,582 Cost: $185,704 |
$56,975 | 481,456 | $38,607 | - | $56,975 481,456 kWh |
$38,607 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $47,255 Cost: $27,390 |
$8,648 | 72,055 | $38,607 | - | $8,648 72,055 kWh |
$38,607 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Administrative Changes | Electricity Usage | Administrative Changes |