IAC Assessment: GT0937
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: GT0937
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Georgia Institute of Technology
Assessment Year 2019
Principal Product large seam pipes
NAICS 331210 - Iron and Steel Pipe and Tube Manufacturing from Purchased Steel
SIC 3312 - Blast Furnaces And Steel Mills
Sales $50,000,000-$100,000,000
# of Employees 300
Plant Area (Sq.Ft.) 640,000
Annual Production 38,769 Units
Production Hrs. Annual 3,648
Location (State) FL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $638,133 6,124,631 kWh $0.10
Natural Gas $292,787 49,679 MMBtu $5.89
TOTAL ENERGY COSTS $930,920
RECOMMENDED SAVINGS* $65,037 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,907
#|Description Savings
Cost
Status Electricity Usage Electricity Fees Natural Gas Electricity Usage Electricity Fees Natural Gas
$ kWh $ $ $ MMBtu
01: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,362
Cost:
$310
$1,362 13,097 - - - - $1,362
13,097
kWh
-
-
$
-
-
MMBtu
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,545
Cost:
$4,311
$2,545 24,474 - - - - $2,545
24,474
kWh
-
-
$
-
-
MMBtu
03: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$10,618
Cost:
$38,920
- - $10,618 - - - -
-
kWh
$10,618
-
$
-
-
MMBtu
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$32,772
Cost:
$100,000
- - - - $32,772 5,564 -
-
kWh
-
-
$
$32,772
5,564
MMBtu
05: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$17,740
Cost:
$158,500
$17,740 170,261 - - - - $17,740
170,261
kWh
-
-
$
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$65,037
Cost:
$302,041
$21,647 207,832 $10,618 - $32,772 5,564 $21,647
207,832
kWh
$10,618
-
$
$32,772
5,564
MMBtu
TOTAL IMPLEMENTED Savings:
$3,907
Cost:
$4,621
$3,907 37,571 - - - - $3,907
37,571
kWh
-
-
$
-
-
MMBtu
Savings
Cost
$ kWh $ $ $ MMBtu
Electricity Usage Electricity Fees Natural Gas Electricity Usage Electricity Fees Natural Gas