Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 2023 |
Principal Product | School Buses |
NAICS | 336211 - Motor Vehicle Body Manufacturing |
SIC | 3713 - Truck And Bus Bodies |
Sales | >$500,000,000 |
# of Employees | 1,200 |
Plant Area (Sq.Ft.) | 1,000,000 |
Annual Production | 6,727 Units |
Production Hrs. Annual | 2,500 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,522,135 | 21,337,881 | kWh | $0.07 |
Natural Gas | $933,982 | 103,204 | MMBtu | $9.05 |
TOTAL ENERGY COSTS | $2,456,117 | |||
RECOMMENDED SAVINGS* | $405,892 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $246,074 |
#|Description |
Savings Cost |
Status | Electricity Usage | Personnel Changes | Electricity Usage | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $64,657 Cost: $1,850 |
$67,557 | 965,109 | $(-2,900) | - |
$67,557 965,109 kWh |
$(-2,900) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $104,725 Cost: $13,000 |
$104,725 | 1,475,000 | - | - |
$104,725 1,475,000 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $73,640 Cost: $23,680 |
$73,640 | 1,037,184 | - | - |
$73,640 1,037,184 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $3,052 Cost: $3,250 |
$3,052 | 42,981 | - | - |
$3,052 42,981 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $159,818 Cost: $4,611,930 |
$159,818 | 2,240,394 | - | - |
$159,818 2,240,394 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $405,892 Cost: $4,653,710 |
$408,792 | 5,760,668 | $(-2,900) | - | $408,792 5,760,668 kWh |
$(-2,900) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $246,074 Cost: $41,780 |
$248,974 | 3,520,274 | $(-2,900) | - | $248,974 3,520,274 kWh |
$(-2,900) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Personnel Changes | Electricity Usage | Personnel Changes |