Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 2024 |
Principal Product | Animal Fats and Vegetable Oils |
NAICS | 311613 - Rendering and Meat Byproduct Processing |
SIC | 2077 - Animal And Marine Fats And Oils |
Sales | $10,000,000-$50,000,000 |
# of Employees | 19 |
Plant Area (Sq.Ft.) | 15,000 |
Annual Production | 55,401,409 Pounds |
Production Hrs. Annual | 5,600 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $47,324 | 300,054 | kWh | $0.16 |
Natural Gas | $80,560 | 18,953 | MMBtu | $4.25 |
TOTAL ENERGY COSTS | $187,738 | |||
RECOMMENDED SAVINGS* | $114,916 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Water Usage | Other Liquid (non-haz) | Personnel Changes | Electricity Usage | Natural Gas | Water Usage | Other Liquid (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | Tgal | $ | gal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7132 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS |
Savings: $442 Cost: $197 |
$442 | 2,799 | - | - | - | - | - | - | - | - |
$442 2,799 kWh |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $3,668 Cost: $2,732 |
- | - | $3,668 | 863 | - | - | - | - | - | - |
- - kWh |
$3,668 863 MMBtu |
- - Tgal |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,280 Cost: $1,334 |
$1,280 | 8,100 | - | - | - | - | - | - | - | - |
$1,280 8,100 kWh |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $39,992 Cost: $87,500 |
$44,240 | 280,000 | $(-4,248) | (-1,000) | - | - | - | - | - | - |
$44,240 280,000 kWh |
$(-4,248) (-1,000) MMBtu |
- - Tgal |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $770 Cost: $1,850 |
- | - | $3,590 | 845 | - | - | - | - | $(-2,820) | - |
- - kWh |
$3,590 845 MMBtu |
- - Tgal |
- - gal |
$(-2,820) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2128 USE STEAM CONDENSATE FOR HOT WATER SUPPLY (NON-POTABLE) |
Savings: $4,603 Cost: $11,665 |
- | - | $4,603 | 1,083 | - | - | - | - | - | - |
- - kWh |
$4,603 1,083 MMBtu |
- - Tgal |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.4151 MINIMIZE WATER USAGE |
Savings: $64,161 Cost: $237,800 |
- | - | - | - | $4,357 | 239 | $59,854 | 239,417 | $(-50) | - |
- - kWh |
- - MMBtu |
$4,357 239 Tgal |
$59,854 239,417 gal |
$(-50) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $114,916 Cost: $343,078 |
$45,962 | 290,899 | $7,613 | 1,791 | $4,357 | 239 | $59,854 | 239,417 | $(-2,870) | - | $45,962 290,899 kWh |
$7,613 1,791 MMBtu |
$4,357 239 Tgal |
$59,854 239,417 gal |
$(-2,870) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | Tgal | $ | gal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Water Usage | Other Liquid (non-haz) | Personnel Changes | Electricity Usage | Natural Gas | Water Usage | Other Liquid (non-haz) | Personnel Changes |