IAC Assessment: HO0161
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: HO0161
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Hofstra Univ.
Assessment Year 1997
Principal Product Threads
NAICS n/a
SIC 2282 - Throwing And Winding Mills
Sales $1,000,000-$5,000,000
# of Employees 67
Plant Area (Sq.Ft.) 100,000
Annual Production 250,000 Units
Production Hrs. Annual 6,600
Location (State) PA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $136,838 3,048,652 kWh $0.04
Electricity Demand $23,275 6,552 kW-months/year $3.55
Electricity Fees $31,139 - $ -
Natural Gas $26,072 6,192 MMBtu $4.21
TOTAL ENERGY COSTS $217,324
RECOMMENDED SAVINGS* $28,200 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $19,065
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Primary Raw Material Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Primary Raw Material
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,362
Cost:
$11,311
$4,680 104,338 $682 192 - - - - - - - - $4,680
104,338
kWh
$682
192
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$3,635
Cost:
$1,878
- - - - $3,635 863 - - - - - - -
-
kWh
-
-
kW-months/year
$3,635
863
MMBtu
-
-
$
-
-
$
-
-
$
03: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$723
Cost:
$385
- - - - $723 172 - - - - - - -
-
kWh
-
-
kW-months/year
$723
172
MMBtu
-
-
$
-
-
$
-
-
$
04: 2.1223 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) Savings:
$4,370
Cost:
$5,000
- - - - $4,370 1,038 - - - - - - -
-
kWh
-
-
kW-months/year
$4,370
1,038
MMBtu
-
-
$
-
-
$
-
-
$
05: 4.432 CROSS-TRAIN PERSONNEL TO AVOID LOST TIME Savings:
$480
Cost:
$100
- - - - - - $480 - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$480
-
$
-
-
$
-
-
$
06: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) Savings:
$1,130
Cost:
$100
- - - - - - - - $1,130 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
$1,130
-
$
-
-
$
07: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS Savings:
$12,500
Cost:
$2,000
- - - - - - - - - - $12,500 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
$12,500
-
$
TOTAL RECOMMENDED Savings:
$28,200
Cost:
$20,774
$4,680 104,338 $682 192 $8,728 2,073 $480 - $1,130 - $12,500 - $4,680
104,338
kWh
$682
192
kW-months/year
$8,728
2,073
MMBtu
$480
-
$
$1,130
-
$
$12,500
-
$
TOTAL IMPLEMENTED Savings:
$19,065
Cost:
$13,796
$4,680 104,338 $682 192 $723 172 $480 - - - $12,500 - $4,680
104,338
kWh
$682
192
kW-months/year
$723
172
MMBtu
$480
-
$
-
-
$
$12,500
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Primary Raw Material Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Primary Raw Material