IAC Assessment: HO0167
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: HO0167
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Hofstra Univ.
Assessment Year 1998
Principal Product Waste reduction equipment
NAICS n/a
SIC 3359 -
Sales $5,000,000-$10,000,000
# of Employees 55
Plant Area (Sq.Ft.) 65,000
Annual Production 200 Pieces
Production Hrs. Annual 2,210
Location (State) PA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $45,960 536,342 kWh $0.09
Electricity Demand $23,695 2,048 kW-months/year $11.57
Electricity Fees $(-2,599) - $ -
Natural Gas $17,646 2,884 MMBtu $6.12
TOTAL ENERGY COSTS $84,702
RECOMMENDED SAVINGS* $27,599 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Electricity Usage Electricity Demand Natural Gas Personnel Changes
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$11,801
Cost:
$37,734
$6,803 79,426 $4,998 432 - - - - $6,803
79,426
kWh
$4,998
432
kW-months/year
-
-
MMBtu
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,615
Cost:
$6,215
$2,088 24,326 $1,527 132 - - - - $2,088
24,326
kWh
$1,527
132
kW-months/year
-
-
MMBtu
-
-
$
03: 2.7231 USE RADIANT HEATER FOR SPOT HEATING Savings:
$3,129
Cost:
$6,600
- - - - $3,129 511 - - -
-
kWh
-
-
kW-months/year
$3,129
511
MMBtu
-
-
$
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$2,275
Cost:
$1,400
$2,275 26,671 - - - - - - $2,275
26,671
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
05: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$530
Cost:
-
$530 6,155 - - - - - - $530
6,155
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
06: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$1,269
Cost:
$30
$733 8,499 $536 46 - - - - $733
8,499
kWh
$536
46
kW-months/year
-
-
MMBtu
-
-
$
07: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP Savings:
$2,240
Cost:
$9,000
$1,296 24,033 $944 82 - - - - $1,296
24,033
kWh
$944
82
kW-months/year
-
-
MMBtu
-
-
$
08: 4.211 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE Savings:
$1,765
Cost:
$500
- - - - - - $1,765 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,765
-
$
09: 4.423 MOVE PRODUCT USING MECHANICAL MEANS Savings:
$975
Cost:
$100
- - - - - - $975 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$975
-
$
TOTAL RECOMMENDED Savings:
$27,599
Cost:
$61,579
$13,725 169,110 $8,005 692 $3,129 511 $2,740 - $13,725
169,110
kWh
$8,005
692
kW-months/year
$3,129
511
MMBtu
$2,740
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Electricity Usage Electricity Demand Natural Gas Personnel Changes