Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Hofstra Univ. |
---|---|
Assessment Year | 1999 |
Principal Product | Composite Plastics |
NAICS | n/a |
SIC | 3083 - Laminated Plastics Plate & Sheet |
Sales | $5,000,000-$10,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 64,000 |
Annual Production | 45 Tons |
Production Hrs. Annual | 6,000 |
Location (State) | NJ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $87,863 | 1,047,773 | kWh | $0.08 |
Electricity Demand | $37,730 | 3,439 | kW-months/year | $10.97 |
Electricity Fees | $10,649 | - | $ | - |
Natural Gas | $50,157 | 9,905 | MMBtu | $5.06 |
TOTAL ENERGY COSTS | $205,119 | |||
RECOMMENDED SAVINGS* | $19,159 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $10,287 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,758 Cost: $16,993 |
$3,692 | 43,962 | $2,066 | 184 | - | - | - | - | - | - |
$3,692 43,962 kWh |
$2,066 184 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $785 Cost: $1,000 |
$506 | 6,155 | $279 | 25 | - | - | - | - | - | - |
$506 6,155 kWh |
$279 25 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,524 Cost: $360 |
$1,524 | 16,706 | - | - | - | - | - | - | - | - |
$1,524 16,706 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7496 INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE |
Savings: $395 Cost: $400 |
- | - | - | - | $395 | 163 | - | - | - | - |
- - kWh |
- - kW-months/year |
$395 163 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7233 USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT |
Savings: $825 Cost: $2,000 |
- | - | - | - | $825 | 340 | - | - | - | - |
- - kWh |
- - kW-months/year |
$825 340 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $1,000 Cost: $300 |
- | - | - | - | - | - | - | - | $1,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$1,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS |
Savings: $1,872 Cost: $3,500 |
- | - | - | - | - | - | $1,872 | 262,080 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,872 262,080 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.123 REDUCE DEFECTS BY REDUCING PRODUCT TIPPING |
Savings: $2,000 Cost: $10,000 |
- | - | - | - | - | - | - | - | $2,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$2,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.123 REDUCE DEFECTS BY REDUCING PRODUCT TIPPING |
Savings: $5,000 Cost: $3,000 |
- | - | - | - | - | - | - | - | $5,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$5,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $19,159 Cost: $37,553 |
$5,722 | 66,823 | $2,345 | 209 | $1,220 | 503 | $1,872 | 262,080 | $8,000 | - | $5,722 66,823 kWh |
$2,345 209 kW-months/year |
$1,220 503 MMBtu |
$1,872 262,080 lb |
$8,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $10,287 Cost: $21,053 |
$5,722 | 66,823 | $2,345 | 209 | $1,220 | 503 | - | - | $1,000 | - | $5,722 66,823 kWh |
$2,345 209 kW-months/year |
$1,220 503 MMBtu |
- - lb |
$1,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | One-time Revenue or Avoided Cost |