Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 1994 |
Principal Product | hard candy, licorice |
NAICS | n/a |
SIC | 2064 - Candy & Other Confectionery Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 154,000 |
Annual Production | 20,000,000 Pounds |
Production Hrs. Annual | 3,768 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $157,007 | 2,939,332 | kWh | $0.05 |
Natural Gas | $138,288 | 34,575 | MMBtu | $4.00 |
TOTAL ENERGY COSTS | $295,295 | |||
RECOMMENDED SAVINGS* | $62,755 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $5,165 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Water Consumption | Electricity Usage | Natural Gas | Administrative Changes | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER |
Savings: $24,202 Cost: $11,700 |
- | - | - | - | $24,202 | - | - | - |
- - kWh |
- - MMBtu |
$24,202 - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.4114 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER |
Savings: $19,667 Cost: $41,400 |
$(-3,459) | (-64,771) | - | - | - | - | $23,126 | - |
$(-3,459) (-64,771) kWh |
- - MMBtu |
- - $ |
$23,126 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4321 UPGRADE OBSOLETE EQUIPMENT |
Savings: $11,900 Cost: $12,650 |
- | - | $11,900 | 2,975 | - | - | - | - |
- - kWh |
$11,900 2,975 MMBtu |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,432 Cost: $655 |
$2,432 | 45,428 | - | - | - | - | - | - |
$2,432 45,428 kWh |
- - MMBtu |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,843 Cost: $2,035 |
$1,843 | 34,584 | - | - | - | - | - | - |
$1,843 34,584 kWh |
- - MMBtu |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,092 Cost: $400 |
$1,092 | 20,516 | - | - | - | - | - | - |
$1,092 20,516 kWh |
- - MMBtu |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $890 Cost: $500 |
$890 | 16,706 | - | - | - | - | - | - |
$890 16,706 kWh |
- - MMBtu |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE |
Savings: $593 Cost: $880 |
- | - | $593 | 148 | - | - | - | - |
- - kWh |
$593 148 MMBtu |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $136 Cost: $250 |
- | - | - | - | $136 | - | - | - |
- - kWh |
- - MMBtu |
$136 - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $62,755 Cost: $70,470 |
$2,798 | 52,463 | $12,493 | 3,123 | $24,338 | - | $23,126 | - | $2,798 52,463 kWh |
$12,493 3,123 MMBtu |
$24,338 - $ |
$23,126 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $5,165 Cost: $3,190 |
$5,165 | 96,718 | - | - | - | - | - | - | $5,165 96,718 kWh |
- - MMBtu |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Water Consumption | Electricity Usage | Natural Gas | Administrative Changes | Water Consumption |