IAC Assessment: IA0147
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: IA0147
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Iowa State University
Assessment Year 1996
Principal Product Custom Plastic Moldings
NAICS n/a
SIC 3089 - Plastics Products, Nec
Sales $5,000,000-$10,000,000
# of Employees 95
Plant Area (Sq.Ft.) 35,000
Annual Production 1,250,000 Pounds
Production Hrs. Annual 6,120
Location (State) NE
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $99,601 2,078,839 kWh $0.05
Electricity Demand $4,975 5,616 kW-months/year $0.89
Electricity Fees $2,274 - $ -
Natural Gas $6,847 1,907 MMBtu $3.59
TOTAL ENERGY COSTS $122,086
RECOMMENDED SAVINGS* $4,652 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $4,207
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Electricity Usage Electricity Demand Solid Waste (non-haz)
$ kWh $ kW-months/year $ lb
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$3,007
Cost:
$50
$2,902 60,668 $105 119 - - $2,902
60,668
kWh
$105
119
kW-months/year
-
-
lb
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$660
Cost:
$217
$638 13,189 $22 25 - - $638
13,189
kWh
$22
25
kW-months/year
-
-
lb
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$540
Cost:
$169
$521 10,844 $19 22 - - $521
10,844
kWh
$19
22
kW-months/year
-
-
lb
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$296
Cost:
$268
$286 5,862 $10 11 - - $286
5,862
kWh
$10
11
kW-months/year
-
-
lb
05: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS Savings:
$149
Cost:
$100
- - - - $149 20,720 -
-
kWh
-
-
kW-months/year
$149
20,720
lb
TOTAL RECOMMENDED Savings:
$4,652
Cost:
$804
$4,347 90,563 $156 177 $149 20,720 $4,347
90,563
kWh
$156
177
kW-months/year
$149
20,720
lb
TOTAL IMPLEMENTED Savings:
$4,207
Cost:
$436
$4,061 84,701 $146 166 - - $4,061
84,701
kWh
$146
166
kW-months/year
-
-
lb
Savings
Cost
$ kWh $ kW-months/year $ lb
Electricity Usage Electricity Demand Solid Waste (non-haz) Electricity Usage Electricity Demand Solid Waste (non-haz)