IAC logo
IAC Assessment: IA0150
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: IA0150
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Iowa State University
Assessment Year 1996
Principal Product Edible Stocks and Broths
NAICS n/a
SIC 2099 - Food Preparations, Nec
Sales $10,000,000-$50,000,000
# of Employees 50
Plant Area (Sq.Ft.) 64,000
Annual Production 45,000,000 Pounds
Production Hrs. Annual 6,120
Location (State) IA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $144,740 4,458,968 kWh $0.03
Electricity Demand $32,297 10,272 kW-months/year $3.14
Electricity Fees $785 - $ -
Natural Gas $335,200 172,147 MMBtu $1.95
TOTAL ENERGY COSTS $525,622
RECOMMENDED SAVINGS* $11,369 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $10,964
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Administrative Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $
01: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$6,888
Cost:
$1,000
- - - - $6,888 3,532 - - - - -
-
kWh
-
-
kW-months/year
$6,888
3,532
MMBtu
-
-
Tgal
-
-
$
02: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE Savings:
$850
Cost:
$165
- - - - $850 436 - - - - -
-
kWh
-
-
kW-months/year
$850
436
MMBtu
-
-
Tgal
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$405
Cost:
$1,186
$320 15,533 $85 31 - - - - - - $320
15,533
kWh
$85
31
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$350
Cost:
$229
$271 13,189 $79 29 - - - - - - $271
13,189
kWh
$79
29
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
05: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES Savings:
$356
Cost:
-
- - - - - - - - $356 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$356
-
$
06: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION Savings:
$2,520
Cost:
$2,500
- - - - - - $2,520 1,200,000 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$2,520
1,200,000
Tgal
-
-
$
TOTAL RECOMMENDED Savings:
$11,369
Cost:
$5,080
$591 28,722 $164 60 $7,738 3,968 $2,520 1,200,000 $356 - $591
28,722
kWh
$164
60
kW-months/year
$7,738
3,968
MMBtu
$2,520
1,200,000
Tgal
$356
-
$
TOTAL IMPLEMENTED Savings:
$10,964
Cost:
$3,894
$271 13,189 $79 29 $7,738 3,968 $2,520 1,200,000 $356 - $271
13,189
kWh
$79
29
kW-months/year
$7,738
3,968
MMBtu
$2,520
1,200,000
Tgal
$356
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Administrative Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Administrative Changes