IAC Assessment: IA0223
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: IA0223
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Iowa State University
Assessment Year 1999
Principal Product vending machines
NAICS n/a
SIC 3581 - Automatic Vending Machines
Sales $50,000,000-$100,000,000
# of Employees 425
Plant Area (Sq.Ft.) 375,000
Annual Production 30,000 Pieces
Production Hrs. Annual 7,056
Location (State) IA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $108,409 4,087,339 kWh $0.03
Electricity Demand $79,016 11,352 kW-months/year $6.96
Natural Gas $106,250 21,802 MMBtu $4.87
TOTAL ENERGY COSTS $311,099
RECOMMENDED SAVINGS* $146,692 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$9,307
Cost:
$2,670
$(-55) (-1,465) - - $9,362 3,657 - - - - - - $(-55)
(-1,465)
kWh
-
-
kW-months/year
$9,362
3,657
MMBtu
-
-
lb
-
-
$
-
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,129
Cost:
$275
$1,319 50,410 $810 86 - - - - - - - - $1,319
50,410
kWh
$810
86
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,841
Cost:
-
$671 25,791 $1,170 125 - - - - - - - - $671
25,791
kWh
$1,170
125
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,282
Cost:
$653
$797 30,481 $485 53 - - - - - - - - $797
30,481
kWh
$485
53
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$741
Cost:
$50
$460 17,585 $281 30 - - - - - - - - $460
17,585
kWh
$281
30
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
06: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$144
Cost:
$732
$144 5,569 - - - - - - - - - - $144
5,569
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
07: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$17,424
Cost:
$7,400
- - - - - - $17,424 588,000 - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$17,424
588,000
lb
-
-
$
-
-
$
08: 4.322 ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL Savings:
$70,029
Cost:
$25,372
- - - - - - - - $70,029 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
$70,029
-
$
-
-
$
09: 4.514 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS Savings:
$40,016
Cost:
$218
- - - - - - - - $40,016 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
$40,016
-
$
-
-
$
10: 4.211 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE Savings:
$3,779
Cost:
$1,400
- - - - - - - - - - $3,779 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
$3,779
-
$
TOTAL RECOMMENDED Savings:
$146,692
Cost:
$38,770
$3,336 128,371 $2,746 294 $9,362 3,657 $17,424 588,000 $110,045 - $3,779 - $3,336
128,371
kWh
$2,746
294
kW-months/year
$9,362
3,657
MMBtu
$17,424
588,000
lb
$110,045
-
$
$3,779
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Ancillary Material Cost