IAC Assessment: IA0236
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: IA0236
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Iowa State University
Assessment Year 1999
Principal Product custom steel plate
NAICS n/a
SIC 3441 - Fabricated Structural Metal
Sales $50,000,000-$100,000,000
# of Employees 210
Plant Area (Sq.Ft.) 336,000
Annual Production 500 Tons
Production Hrs. Annual 4,160
Location (State) IA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $98,717 3,869,871 kWh $0.03
Electricity Demand $86,557 12,432 kW-months/year $6.96
Natural Gas $76,992 22,355 MMBtu $3.44
TOTAL ENERGY COSTS $267,847
RECOMMENDED SAVINGS* $19,626 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Other Liquid (haz) Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Other Liquid (haz) Personnel Changes Primary Raw Material
$ kWh $ kW-months/year $ gal $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,665
Cost:
$16,153
$2,226 88,218 $2,439 350 - - - - - - $2,226
88,218
kWh
$2,439
350
kW-months/year
-
-
gal
-
-
$
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,409
Cost:
$1,248
$1,897 75,322 $1,512 217 - - - - - - $1,897
75,322
kWh
$1,512
217
kW-months/year
-
-
gal
-
-
$
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,131
Cost:
$394
$1,187 47,186 $944 136 - - - - - - $1,187
47,186
kWh
$944
136
kW-months/year
-
-
gal
-
-
$
-
-
$
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$455
Cost:
$200
$455 18,171 - - - - - - - - $455
18,171
kWh
-
-
kW-months/year
-
-
gal
-
-
$
-
-
$
05: 3.8143 RECYCLE CLEANING SOLVENT AND REUSE Savings:
$8,966
Cost:
$7,853
- - $(-418) (-60) $7,859 594 $(-567) - $2,092 - -
-
kWh
$(-418)
(-60)
kW-months/year
$7,859
594
gal
$(-567)
-
$
$2,092
-
$
TOTAL RECOMMENDED Savings:
$19,626
Cost:
$25,848
$5,765 228,897 $4,477 643 $7,859 594 $(-567) - $2,092 - $5,765
228,897
kWh
$4,477
643
kW-months/year
$7,859
594
gal
$(-567)
-
$
$2,092
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
gal
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ gal $ $ $ $
Electricity Usage Electricity Demand Other Liquid (haz) Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Other Liquid (haz) Personnel Changes Primary Raw Material