Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 1999 |
Principal Product | custom steel plate |
NAICS | n/a |
SIC | 3441 - Fabricated Structural Metal |
Sales | $50,000,000-$100,000,000 |
# of Employees | 210 |
Plant Area (Sq.Ft.) | 336,000 |
Annual Production | 500 Tons |
Production Hrs. Annual | 4,160 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $98,717 | 3,869,871 | kWh | $0.03 |
Electricity Demand | $86,557 | 12,432 | kW-months/year | $6.96 |
Natural Gas | $76,992 | 22,355 | MMBtu | $3.44 |
TOTAL ENERGY COSTS | $267,847 | |||
RECOMMENDED SAVINGS* | $19,626 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Liquid (haz) | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Other Liquid (haz) | Personnel Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | gal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,665 Cost: $16,153 |
$2,226 | 88,218 | $2,439 | 350 | - | - | - | - | - | - |
$2,226 88,218 kWh |
$2,439 350 kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,409 Cost: $1,248 |
$1,897 | 75,322 | $1,512 | 217 | - | - | - | - | - | - |
$1,897 75,322 kWh |
$1,512 217 kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,131 Cost: $394 |
$1,187 | 47,186 | $944 | 136 | - | - | - | - | - | - |
$1,187 47,186 kWh |
$944 136 kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $455 Cost: $200 |
$455 | 18,171 | - | - | - | - | - | - | - | - |
$455 18,171 kWh |
- - kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.8143 RECYCLE CLEANING SOLVENT AND REUSE |
Savings: $8,966 Cost: $7,853 |
- | - | $(-418) | (-60) | $7,859 | 594 | $(-567) | - | $2,092 | - |
- - kWh |
$(-418) (-60) kW-months/year |
$7,859 594 gal |
$(-567) - $ |
$2,092 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $19,626 Cost: $25,848 |
$5,765 | 228,897 | $4,477 | 643 | $7,859 | 594 | $(-567) | - | $2,092 | - | $5,765 228,897 kWh |
$4,477 643 kW-months/year |
$7,859 594 gal |
$(-567) - $ |
$2,092 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | gal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Liquid (haz) | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Other Liquid (haz) | Personnel Changes | Primary Raw Material |