IAC Assessment: IA0258
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: IA0258
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Iowa State University
Assessment Year 2000
Principal Product refrigerated displays
NAICS n/a
SIC 3589 - Service Industry Machinery, Nec
Sales $10,000,000-$50,000,000
# of Employees 400
Plant Area (Sq.Ft.) 120,000
Annual Production 6,500 Pieces
Production Hrs. Annual 8,760
Location (State) IA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $59,182 1,631,008 kWh $0.04
Electricity Demand $37,154 4,584 kW-months/year $8.11
Natural Gas $21,690 4,302 MMBtu $5.04
TOTAL ENERGY COSTS $119,732
RECOMMENDED SAVINGS* $133,197 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $5,078
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (non-haz) Water Consumption Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (non-haz) Water Consumption
$ kWh $ kW-months/year $ MMBtu $ Tgal $ gal $ Tgal
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$23,446
Cost:
$45,125
$13,005 358,148 $10,441 1,289 - - - - - - - - $13,005
358,148
kWh
$10,441
1,289
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
Tgal
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,870
Cost:
$753
$1,866 51,290 $1,004 124 - - - - - - - - $1,866
51,290
kWh
$1,004
124
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
Tgal
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$986
Cost:
$40
$756 20,223 $230 29 - - - - - - - - $756
20,223
kWh
$230
29
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
Tgal
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$288
Cost:
$25
$223 6,155 $65 8 - - - - - - - - $223
6,155
kWh
$65
8
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
Tgal
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,920
Cost:
$1,206
- - - - $1,920 393 - - - - - - -
-
kWh
-
-
kW-months/year
$1,920
393
MMBtu
-
-
Tgal
-
-
gal
-
-
Tgal
06: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS Savings:
$47,250
Cost:
$7,175
- - - - - - - - $47,250 2,250 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$47,250
2,250
gal
-
-
Tgal
07: 3.8211 CONVERT TO AQUEOUS CLEANING SYSTEM Savings:
$56,437
Cost:
$420
- - - - - - $(-5) (-16,250) $56,453 9,750 $(-11) - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$(-5)
(-16,250)
Tgal
$56,453
9,750
gal
$(-11)
-
Tgal
TOTAL RECOMMENDED Savings:
$133,197
Cost:
$54,744
$15,850 435,816 $11,740 1,450 $1,920 393 $(-5) (-16,250) $103,703 12,000 $(-11) - $15,850
435,816
kWh
$11,740
1,450
kW-months/year
$1,920
393
MMBtu
$(-5)
(-16,250)
Tgal
$103,703
12,000
gal
$(-11)
-
Tgal
TOTAL IMPLEMENTED Savings:
$5,078
Cost:
$1,984
$2,089 57,445 $1,069 132 $1,920 393 - - - - - - $2,089
57,445
kWh
$1,069
132
kW-months/year
$1,920
393
MMBtu
-
-
Tgal
-
-
gal
-
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ gal $ Tgal
Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (non-haz) Water Consumption Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (non-haz) Water Consumption