Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 2001 |
Principal Product | vinyl windows |
NAICS | n/a |
SIC | 2431 - Millwork |
Sales | $10,000,000-$50,000,000 |
# of Employees | 180 |
Plant Area (Sq.Ft.) | 175,000 |
Annual Production | 450,000 Pieces |
Production Hrs. Annual | 5,120 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $52,548 | 2,264,094 | kWh | $0.02 |
Electricity Demand | $35,169 | 5,940 | kW-months/year | $5.92 |
Natural Gas | $27,822 | 4,728 | MMBtu | $5.88 |
TOTAL ENERGY COSTS | $121,042 | |||
RECOMMENDED SAVINGS* | $135,527 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $36,188 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,585 Cost: $989 |
$4,150 | 179,634 | $2,435 | 415 | - | - | - | - | - | - |
$4,150 179,634 kWh |
$2,435 415 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $512 Cost: $116 |
$348 | 15,051 | $164 | 28 | - | - | - | - | - | - |
$348 15,051 kWh |
$164 28 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,284 Cost: $887 |
$1,439 | 62,280 | $845 | 144 | - | - | - | - | - | - |
$1,439 62,280 kWh |
$845 144 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5215 AVOID CONTAMINATION OF END PIECES AND REUSE AS FEED STOCK |
Savings: $18,000 Cost: $22,100 |
- | - | - | - | $18,000 | 922,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
$18,000 922,000 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.423 MOVE PRODUCT USING MECHANICAL MEANS |
Savings: $96,543 Cost: $50,000 |
- | - | - | - | - | - | $94,043 | - | $2,500 | - |
- - kWh |
- - kW-months/year |
- - lb |
$94,043 - $ |
$2,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.322 ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL |
Savings: $11,603 Cost: $1,088 |
- | - | - | - | - | - | $11,603 | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
$11,603 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $135,527 Cost: $75,180 |
$5,937 | 256,965 | $3,444 | 587 | $18,000 | 922,000 | $105,646 | - | $2,500 | - | $5,937 256,965 kWh |
$3,444 587 kW-months/year |
$18,000 922,000 lb |
$105,646 - $ |
$2,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $36,188 Cost: $24,177 |
$4,150 | 179,634 | $2,435 | 415 | $18,000 | 922,000 | $11,603 | - | - | - | $4,150 179,634 kWh |
$2,435 415 kW-months/year |
$18,000 922,000 lb |
$11,603 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |