IAC Assessment: IA0285
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: IA0285
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Iowa State University
Assessment Year 2002
Principal Product Hydrants, valves, pumps
NAICS n/a
SIC 3494 - Valves And Pipe Fittings, Nec
Sales $100,000,000-$500,000,000
# of Employees 370
Plant Area (Sq.Ft.) 140,000
Annual Production 211,000 Pieces
Production Hrs. Annual 6,240
Location (State) MN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $125,955 3,661,840 kWh $0.03
Electricity Demand $63,315 8,412 kW-months/year $7.53
Natural Gas $97,412 9,901 MMBtu $9.84
TOTAL ENERGY COSTS $403,654
RECOMMENDED SAVINGS* $108,276 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $107,021
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Electricity Usage Electricity Demand Solid Waste (non-haz)
$ kWh $ kW-months/year $ lb
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,274
Cost:
$458
$1,990 68,134 $1,284 131 - - $1,990
68,134
kWh
$1,284
131
kW-months/year
-
-
lb
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$806
Cost:
$237
$489 16,745 $317 32 - - $489
16,745
kWh
$317
32
kW-months/year
-
-
lb
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$449
Cost:
$92
$273 9,360 $176 18 - - $273
9,360
kWh
$176
18
kW-months/year
-
-
lb
04: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$39,507
Cost:
$800
- - $39,507 4,032 - - -
-
kWh
$39,507
4,032
kW-months/year
-
-
lb
05: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$46,580
Cost:
$320
- - - - $46,580 - -
-
kWh
-
-
kW-months/year
$46,580
-
lb
06: 3.7198 REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT Savings:
$12,642
Cost:
$3,424
- - - - $12,642 - -
-
kWh
-
-
kW-months/year
$12,642
-
lb
07: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS Savings:
$5,018
Cost:
$7,500
- - - - $5,018 - -
-
kWh
-
-
kW-months/year
$5,018
-
lb
TOTAL RECOMMENDED Savings:
$108,276
Cost:
$12,831
$2,752 94,239 $41,284 4,213 $64,240 - $2,752
94,239
kWh
$41,284
4,213
kW-months/year
$64,240
-
lb
TOTAL IMPLEMENTED Savings:
$107,021
Cost:
$12,502
$1,990 68,134 $40,791 4,163 $64,240 - $1,990
68,134
kWh
$40,791
4,163
kW-months/year
$64,240
-
lb
Savings
Cost
$ kWh $ kW-months/year $ lb
Electricity Usage Electricity Demand Solid Waste (non-haz) Electricity Usage Electricity Demand Solid Waste (non-haz)