Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 2003 |
Principal Product | Precision Shafts |
NAICS | 336350 - Motor Vehicle Transmission and Power Train Parts Manufacturing |
SIC | 3714 - Motor Vehicle Parts And Accessories |
Sales | $10,000,000-$50,000,000 |
# of Employees | 147 |
Plant Area (Sq.Ft.) | 102,000 |
Annual Production | 5,000,000 Pounds |
Production Hrs. Annual | 4,160 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $147,292 | 4,319,311 | kWh | $0.03 |
Electricity Demand | $51,154 | 14,832 | kW-months/year | $3.45 |
Natural Gas | $47,353 | 9,132 | MMBtu | $5.19 |
TOTAL ENERGY COSTS | $252,302 | |||
RECOMMENDED SAVINGS* | $15,517 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,364 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,975 Cost: $383 |
$1,529 | 44,848 | $446 | 130 | - | - | - | - | - | - |
$1,529 44,848 kWh |
$446 130 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,505 Cost: $415 |
$935 | 27,410 | $570 | 170 | - | - | - | - | - | - |
$935 27,410 kWh |
$570 170 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $551 Cost: $18 |
$348 | 10,192 | $203 | 59 | - | - | - | - | - | - |
$348 10,192 kWh |
$203 59 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $118 Cost: $333 |
$118 | 3,472 | - | - | - | - | - | - | - | - |
$118 3,472 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,381 Cost: $807 |
$1,844 | 54,080 | $537 | 156 | - | - | - | - | - | - |
$1,844 54,080 kWh |
$537 156 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4154 ELIMINATE LEAKS IN WATER LINES AND VALVES |
Savings: $121 Cost: $23 |
- | - | - | - | - | - | $33 | 62,410 | $88 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$33 62,410 Tgal |
$88 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7245 USE DIRECT AIR SUPPLY TO EXHAUST HOODS |
Savings: $5,530 Cost: $2,910 |
- | - | - | - | $5,530 | 1,292 | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,530 1,292 MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $3,336 Cost: $4,442 |
$3,336 | 97,843 | - | - | - | - | - | - | - | - |
$3,336 97,843 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $15,517 Cost: $9,331 |
$8,110 | 237,845 | $1,756 | 515 | $5,530 | 1,292 | $33 | 62,410 | $88 | - | $8,110 237,845 kWh |
$1,756 515 kW-months/year |
$5,530 1,292 MMBtu |
$33 62,410 Tgal |
$88 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,364 Cost: $5,673 |
$7,057 | 206,963 | $1,186 | 345 | - | - | $33 | 62,410 | $88 | - | $7,057 206,963 kWh |
$1,186 345 kW-months/year |
- - MMBtu |
$33 62,410 Tgal |
$88 - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Water Consumption |