Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 2004 |
Principal Product | electric fork trucks |
NAICS | 333924 - Industrial Truck, Tractor, Trailer, and Stacker Machinery Manufacturing |
SIC | 3537 - Industrial Trucks And Tractors |
Sales | $50,000,000-$100,000,000 |
# of Employees | 210 |
Plant Area (Sq.Ft.) | 180,000 |
Annual Production | 8,000 Pieces |
Production Hrs. Annual | 4,836 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $157,078 | 3,935,600 | kWh | $0.04 |
Electricity Demand | $56,996 | 10,852 | kW-months/year | $5.25 |
Natural Gas | $234,586 | 28,795 | MMBtu | $8.15 |
TOTAL ENERGY COSTS | $453,198 | |||
RECOMMENDED SAVINGS* | $56,673 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $45,877 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,846 Cost: $446 |
$1,871 | 60,455 | $1,263 | 150 | - | - | $(-288) | - |
$1,871 60,455 kWh |
$1,263 150 kW-months/year |
- - MMBtu |
$(-288) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,120 Cost: $1,866 |
$550 | 17,711 | $570 | 67 | - | - | - | - |
$550 17,711 kWh |
$570 67 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $125 Cost: $70 |
$62 | 1,992 | $63 | 7 | - | - | - | - |
$62 1,992 kWh |
$63 7 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,173 Cost: $7,306 |
$561 | 18,096 | $885 | 104 | $1,727 | 223 | - | - |
$561 18,096 kWh |
$885 104 kW-months/year |
$1,727 223 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING |
Savings: $817 Cost: $1,230 |
$817 | 26,353 | - | - | - | - | - | - |
$817 26,353 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $8,859 Cost: $9,696 |
$(-155) | (-4,992) | $(-163) | (-19) | $9,177 | 1,198 | - | - |
$(-155) (-4,992) kWh |
$(-163) (-19) kW-months/year |
$9,177 1,198 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $39,733 Cost: $10,000 |
$1,209 | 39,000 | $(-244) | (-29) | $7,568 | 988 | $31,200 | - |
$1,209 39,000 kWh |
$(-244) (-29) kW-months/year |
$7,568 988 MMBtu |
$31,200 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $56,673 Cost: $30,614 |
$4,915 | 158,615 | $2,374 | 281 | $18,472 | 2,409 | $30,912 | - | $4,915 158,615 kWh |
$2,374 281 kW-months/year |
$18,472 2,409 MMBtu |
$30,912 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $45,877 Cost: $17,822 |
$3,703 | 119,543 | $1,967 | 233 | $9,295 | 1,211 | $30,912 | - | $3,703 119,543 kWh |
$1,967 233 kW-months/year |
$9,295 1,211 MMBtu |
$30,912 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes |