IAC Assessment: IA0423
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: IA0423
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Iowa State University
Assessment Year 2008
Principal Product brass and aluminum sand castings
NAICS 331524 - Aluminum Foundries (except Die-Casting)
SIC 3365 - Aluminum Foundries
Sales $5,000,000-$10,000,000
# of Employees 35
Plant Area (Sq.Ft.) 32,000
Annual Production 675,000 Pounds
Production Hrs. Annual 2,500
Location (State) MN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $66,274 1,424,504 kWh $0.05
Electricity Demand $57,212 11,112 kW-months/year $5.15
Electricity Fees $16,202 - $ -
Natural Gas $79,293 8,086 MMBtu $9.81
TOTAL ENERGY COSTS $218,981
RECOMMENDED SAVINGS* $17,168 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,417
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS Savings:
$2,458
Cost:
$617
$1,606 34,473 $852 166 - - $1,606
34,473
kWh
$852
166
kW-months/year
-
-
MMBtu
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$443
Cost:
$25
$288 6,250 $155 30 - - $288
6,250
kWh
$155
30
kW-months/year
-
-
MMBtu
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$1,639
Cost:
$150
$76 1,632 - - $1,563 172 $76
1,632
kWh
-
-
kW-months/year
$1,563
172
MMBtu
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$516
Cost:
$86
$337 7,239 $179 3 - - $337
7,239
kWh
$179
3
kW-months/year
-
-
MMBtu
05: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$697
Cost:
$1,001
$697 14,987 - - - - $697
14,987
kWh
-
-
kW-months/year
-
-
MMBtu
06: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$11,415
Cost:
$18,345
- - - - $11,415 1,253 -
-
kWh
-
-
kW-months/year
$11,415
1,253
MMBtu
TOTAL RECOMMENDED Savings:
$17,168
Cost:
$20,224
$3,004 64,581 $1,186 199 $12,978 1,425 $3,004
64,581
kWh
$1,186
199
kW-months/year
$12,978
1,425
MMBtu
TOTAL IMPLEMENTED Savings:
$3,417
Cost:
$728
$2,231 47,962 $1,186 199 - - $2,231
47,962
kWh
$1,186
199
kW-months/year
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas