Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 2013 |
Principal Product | automotive spark plugs |
NAICS | 336320 - Motor Vehicle Electrical and Electronic Equipment Manufacturing |
SIC | 3694 - Engine Electrical Equipment |
Sales | $50,000,000-$100,000,000 |
# of Employees | 430 |
Plant Area (Sq.Ft.) | 184,000 |
Annual Production | 92,400,000 Pieces |
Production Hrs. Annual | 8,560 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $637,605 | 18,544,050 | kWh | $0.03 |
Electricity Demand | $310,417 | 32,831 | kW-months/year | $9.45 |
Electricity Fees | $192,360 | - | $ | - |
Natural Gas | $446,146 | 76,100 | MMBtu | $5.86 |
TOTAL ENERGY COSTS | $1,586,528 | |||
RECOMMENDED SAVINGS* | $264,697 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $31,266 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7313 RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING |
Savings: $218,077 Cost: $1,045,200 |
- | - | - | - | - | - | $218,077 | 34,940 |
- - kWh |
- - kW-months/year |
- - $ |
$218,077 34,940 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2113 REPAIR OR REPLACE STEAM TRAPS |
Savings: $14,349 Cost: $3,750 |
- | - | - | - | - | - | $14,349 | 2,449 |
- - kWh |
- - kW-months/year |
- - $ |
$14,349 2,449 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE |
Savings: $2,845 Cost: $1,000 |
- | - | - | - | - | - | $2,845 | 485 |
- - kWh |
- - kW-months/year |
- - $ |
$2,845 485 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $6,113 Cost: $6,000 |
- | - | - | - | $6,113 | - | - | - |
- - kWh |
- - kW-months/year |
$6,113 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $689 Cost: $1,590 |
$689 | 20,080 | - | - | - | - | - | - |
$689 20,080 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $6,734 Cost: $5,775 |
$6,734 | 196,327 | - | - | - | - | - | - |
$6,734 196,327 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $598 Cost: $394 |
$386 | 11,268 | $212 | 22 | - | - | - | - |
$386 11,268 kWh |
$212 22 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $3,512 Cost: $1,000 |
- | - | - | - | - | - | $3,512 | 599 |
- - kWh |
- - kW-months/year |
- - $ |
$3,512 599 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $3,758 Cost: $976 |
- | - | - | - | - | - | $3,758 | 641 |
- - kWh |
- - kW-months/year |
- - $ |
$3,758 641 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $8,022 Cost: $210 |
$4,516 | 131,689 | $3,506 | 368 | - | - | - | - |
$4,516 131,689 kWh |
$3,506 368 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $264,697 Cost: $1,065,895 |
$12,325 | 359,364 | $3,718 | 390 | $6,113 | - | $242,541 | 39,114 | $12,325 359,364 kWh |
$3,718 390 kW-months/year |
$6,113 - $ |
$242,541 39,114 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $31,266 Cost: $14,316 |
$689 | 20,080 | - | - | $6,113 | - | $24,464 | 4,174 | $689 20,080 kWh |
- - kW-months/year |
$6,113 - $ |
$24,464 4,174 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas |