IAC Assessment: IA0518
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: IA0518
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Iowa State University
Assessment Year 2014
Principal Product Food Packaging Equipment
NAICS 333993 - Packaging Machinery Manufacturing
SIC 3565 - Packaging Machinery
Sales $50,000,000-$100,000,000
# of Employees 262
Plant Area (Sq.Ft.) 140,000
Annual Production 1,200 Pieces
Production Hrs. Annual 4,368
Location (State) WI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $114,067 1,604,000 kWh $0.07
Electricity Demand $37,712 4,524 kW-months/year $8.34
Electricity Fees $5,598 - $ -
Natural Gas $30,528 4,572 MMBtu $6.68
TOTAL ENERGY COSTS $187,905
RECOMMENDED SAVINGS* $11,135 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $10,209
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,434
Cost:
$704
$2,598 36,512 $836 96 - - $2,598
36,512
kWh
$836
96
kW-months/year
-
-
MMBtu
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,232
Cost:
$5,280
$932 13,104 $300 36 - - $932
13,104
kWh
$300
36
kW-months/year
-
-
MMBtu
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$742
Cost:
$1,050
$561 7,888 $181 22 - - $561
7,888
kWh
$181
22
kW-months/year
-
-
MMBtu
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$939
Cost:
$185
$699 9,841 $240 29 - - $699
9,841
kWh
$240
29
kW-months/year
-
-
MMBtu
05: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$184
Cost:
$140
$139 1,957 $45 5 - - $139
1,957
kWh
$45
5
kW-months/year
-
-
MMBtu
06: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$149
Cost:
$210
$149 2,091 - - - - $149
2,091
kWh
-
-
kW-months/year
-
-
MMBtu
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,190
Cost:
$8,793
$2,190 30,809 - - - - $2,190
30,809
kWh
-
-
kW-months/year
-
-
MMBtu
08: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC Savings:
$462
Cost:
$80
- - - - $462 69 -
-
kWh
-
-
kW-months/year
$462
69
MMBtu
09: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,803
Cost:
$2,302
- - - - $1,803 270 -
-
kWh
-
-
kW-months/year
$1,803
270
MMBtu
TOTAL RECOMMENDED Savings:
$11,135
Cost:
$18,744
$7,268 102,202 $1,602 188 $2,265 339 $7,268
102,202
kWh
$1,602
188
kW-months/year
$2,265
339
MMBtu
TOTAL IMPLEMENTED Savings:
$10,209
Cost:
$17,554
$6,568 92,357 $1,376 161 $2,265 339 $6,568
92,357
kWh
$1,376
161
kW-months/year
$2,265
339
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas