Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Iowa State University |
---|---|
Assessment Year | 2016 |
Principal Product | truck components |
NAICS | 336211 - Motor Vehicle Body Manufacturing |
SIC | 3713 - Truck And Bus Bodies |
Sales | $5,000,000-$10,000,000 |
# of Employees | 165 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 165 Pounds |
Production Hrs. Annual | 6,600 |
Location (State) | IA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $128,894 | 3,436,200 | kWh | $0.04 |
Electricity Demand | $141,907 | 8,304 | kW-months/year | $17.09 |
LPG | $349,358 | 31,899 | MMBtu | $10.95 |
TOTAL ENERGY COSTS | $620,159 | |||
RECOMMENDED SAVINGS* | $74,888 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $49,285 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | LPG | Electricity Usage | Electricity Demand | Electricity Fees | LPG | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $31,455 Cost: $600 |
- | - | - | - | $31,455 | - | - | - |
- - kWh |
- - kW-months/year |
$31,455 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $12,312 Cost: $15,450 |
$5,966 | 159,603 | $6,346 | 371 | - | - | - | - |
$5,966 159,603 kWh |
$6,346 371 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $12,273 Cost: $6,468 |
- | - | - | - | $12,273 | - | - | - |
- - kWh |
- - kW-months/year |
$12,273 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $6,406 Cost: $5,000 |
- | - | - | - | - | - | $6,406 | 585 |
- - kWh |
- - kW-months/year |
- - $ |
$6,406 585 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $4,935 Cost: $672 |
$2,651 | 70,945 | $2,284 | 144 | - | - | - | - |
$2,651 70,945 kWh |
$2,284 144 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,565 Cost: $8,614 |
$1,567 | 41,903 | $1,998 | 116 | - | - | - | - |
$1,567 41,903 kWh |
$1,998 116 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,989 Cost: $60 |
$1,086 | 29,040 | $903 | 52 | - | - | - | - |
$1,086 29,040 kWh |
$903 52 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,623 Cost: $467 |
$884 | 23,628 | $739 | 43 | - | - | - | - |
$884 23,628 kWh |
$739 43 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $330 Cost: $1,200 |
$330 | 8,806 | - | - | - | - | - | - |
$330 8,806 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $74,888 Cost: $38,531 |
$12,484 | 333,925 | $12,270 | 726 | $43,728 | - | $6,406 | 585 | $12,484 333,925 kWh |
$12,270 726 kW-months/year |
$43,728 - $ |
$6,406 585 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $49,285 Cost: $26,331 |
$8,747 | 233,940 | $9,083 | 530 | $31,455 | - | - | - | $8,747 233,940 kWh |
$9,083 530 kW-months/year |
$31,455 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | LPG | Electricity Usage | Electricity Demand | Electricity Fees | LPG |