Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Illinois, Chicago |
---|---|
Assessment Year | 2002 |
Principal Product | Printed Circuit Board Electroplating and Polishing |
NAICS | n/a |
SIC | 3471 - Plating And Polishing |
Sales | $1,000,000-$5,000,000 |
# of Employees | 10 |
Plant Area (Sq.Ft.) | 10,000 |
Annual Production | 2,550 Pieces |
Production Hrs. Annual | 2,168 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $5,348 | 125,933 | kWh | $0.04 |
Electricity Demand | $6,329 | 518 | kW-months/year | $12.22 |
Electricity Fees | $2,194 | - | $ | - |
Natural Gas | $12,260 | 1,558 | MMBtu | $7.87 |
TOTAL ENERGY COSTS | $(-152,517) | |||
RECOMMENDED SAVINGS* | $1,345 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $472 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $873 Cost: $3,949 |
$327 | 6,677 | $451 | 37 | - | - | $17 | - | $78 | - |
$327 6,677 kWh |
$451 37 kW-months/year |
- - MMBtu |
$17 - $ |
$78 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1133 ADJUST BURNERS FOR EFFICIENT OPERATION |
Savings: $472 Cost: $440 |
- | - | - | - | $472 | 60 | - | - | - | - |
- - kWh |
- - kW-months/year |
$472 60 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $1,345 Cost: $4,389 |
$327 | 6,677 | $451 | 37 | $472 | 60 | $17 | - | $78 | - | $327 6,677 kWh |
$451 37 kW-months/year |
$472 60 MMBtu |
$17 - $ |
$78 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $472 Cost: $440 |
- | - | - | - | $472 | 60 | - | - | - | - | - - kWh |
- - kW-months/year |
$472 60 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost |