Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Illinois, Chicago |
---|---|
Assessment Year | 2003 |
Principal Product | Zinc, Aluminum and Magnesium Die Castings |
NAICS | 331523 - Nonferrous Metal Die-Casting Foundries |
SIC | 3364 - Nonferrous Die-casting Exc. Aluminum |
Sales | $50,000,000-$100,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 110,340 |
Annual Production | 1,397,000 Pounds |
Production Hrs. Annual | 3,060 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $202,475 | 6,008,637 | kWh | $0.03 |
Electricity Demand | $172,275 | 12,195 | kW-months/year | $14.13 |
Electricity Fees | $81,756 | - | $ | - |
Natural Gas | $351,471 | 53,783 | MMBtu | $6.53 |
TOTAL ENERGY COSTS | $571,877 | |||
RECOMMENDED SAVINGS* | $126,944 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $7,074 Cost: $11,051 |
$4,318 | 105,318 | - | - | $2,756 | 422 | - | - | - | - | - | - |
$4,318 105,318 kWh |
- - kW-months/year |
$2,756 422 MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,672 Cost: $2,348 |
- | - | - | - | $1,672 | 256 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,672 256 MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $14,194 Cost: $33,428 |
$4,241 | 172,697 | $9,953 | 704 | - | - | - | - | - | - | - | - |
$4,241 172,697 kWh |
$9,953 704 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,069 Cost: $1,299 |
$273 | 6,658 | $129 | 9 | - | - | $267 | - | - | - | $400 | - |
$273 6,658 kWh |
$129 9 kW-months/year |
- - MMBtu |
$267 - $ |
- - $ |
$400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1321 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT |
Savings: $60,387 Cost: $190,035 |
$(-15,513) | (-378,360) | $(-11,530) | (-916) | $82,006 | 14,578 | - | - | - | - | $5,424 | - |
$(-15,513) (-378,360) kWh |
$(-11,530) (-916) kW-months/year |
$82,006 14,578 MMBtu |
- - $ |
- - $ |
$5,424 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2514 COVER OPEN TANKS |
Savings: $22,621 Cost: $19,645 |
$2,810 | 68,530 | - | - | $19,811 | 3,034 | - | - | - | - | - | - |
$2,810 68,530 kWh |
- - kW-months/year |
$19,811 3,034 MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.444 INSTALL SYSTEM TO COLLECT SCRAP |
Savings: $16,357 Cost: $24,000 |
- | - | - | - | - | - | $16,357 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$16,357 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.211 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE |
Savings: $3,570 Cost: - |
- | - | - | - | - | - | - | - | $3,570 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$3,570 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $126,944 Cost: $281,806 |
$(-3,871) | (-25,157) | $(-1,448) | (-203) | $106,245 | 18,290 | $16,624 | - | $3,570 | - | $5,824 | - | $(-3,871) (-25,157) kWh |
$(-1,448) (-203) kW-months/year |
$106,245 18,290 MMBtu |
$16,624 - $ |
$3,570 - $ |
$5,824 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost |