Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Indiana University-Purdue University |
---|---|
Assessment Year | 2015 |
Principal Product | Transmission Seals |
NAICS | 339991 - Gasket, Packing, and Sealing Device Manufacturing |
SIC | 3053 - Gaskets, Packing And Sealing Devices |
Sales | $50,000,000-$100,000,000 |
# of Employees | 493 |
Plant Area (Sq.Ft.) | 185,000 |
Annual Production | 24,637,577 Pieces |
Production Hrs. Annual | 7,488 |
Location (State) | IN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $918,629 | 27,846,000 | kWh | $0.03 |
Electricity Demand | $897,489 | 48,266 | kW-months/year | $18.59 |
Natural Gas | $254,073 | 42,066 | MMBtu | $6.04 |
TOTAL ENERGY COSTS | $2,070,191 | |||
RECOMMENDED SAVINGS* | $184,342 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $5,180 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.8132 USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES |
Savings: $37,208 Cost: - |
- | - | - | - | - | - | - | - | - | - | $37,208 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
$37,208 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.812 APPLY FOR INVESTMENT INCENTIVES |
Savings: $1,728 Cost: - |
- | - | - | - | $1,728 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,728 - $ |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,452 Cost: $99 |
$3,452 | 104,599 | - | - | - | - | - | - | - | - | - | - |
$3,452 104,599 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5242 RECOVER METALS FROM SPENT SOLUTIONS AND RECYCLE |
Savings: $104,502 Cost: $3,200 |
- | - | - | - | - | - | - | - | $104,502 | 468,000 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$104,502 468,000 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $168 Cost: $8 |
$88 | 2,673 | $80 | 4 | - | - | - | - | - | - | - | - |
$88 2,673 kWh |
$80 4 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2531 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR |
Savings: $896 Cost: $212 |
- | - | - | - | - | - | $896 | 148 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$896 148 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $430 Cost: $130 |
$430 | 13,029 | - | - | - | - | - | - | - | - | - | - |
$430 13,029 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $18,251 Cost: $12,039 |
$18,251 | 553,059 | - | - | - | - | - | - | - | - | - | - |
$18,251 553,059 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $15,775 Cost: $32,120 |
$15,775 | 478,023 | - | - | - | - | - | - | - | - | - | - |
$15,775 478,023 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $634 Cost: $1,321 |
$333 | 10,092 | $301 | 16 | - | - | - | - | - | - | - | - |
$333 10,092 kWh |
$301 16 kW-months/year |
- - $ |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.2531 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR |
Savings: $1,298 Cost: $3,968 |
$1,298 | 39,344 | - | - | - | - | - | - | - | - | - | - |
$1,298 39,344 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $184,342 Cost: $53,097 |
$39,627 | 1,200,819 | $381 | 20 | $1,728 | - | $896 | 148 | $104,502 | 468,000 | $37,208 | - | $39,627 1,200,819 kWh |
$381 20 kW-months/year |
$1,728 - $ |
$896 148 MMBtu |
$104,502 468,000 lb |
$37,208 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $5,180 Cost: $99 |
$3,452 | 104,599 | - | - | $1,728 | - | - | - | - | - | - | - | $3,452 104,599 kWh |
- - kW-months/year |
$1,728 - $ |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost |