Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Univ. of Kansas |
---|---|
Assessment Year | 1981 |
Principal Product | ALUMINUM TRUCK BODIES |
NAICS | n/a |
SIC | 3713 - Truck And Bus Bodies |
Sales | $1,000,000-$5,000,000 |
# of Employees | 40 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 1,200 Pieces |
Production Hrs. Annual | 2,000 |
Location (State) | KS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $10,594 | 177,902 | kWh | $0.06 |
Natural Gas | $13,649 | 4,529 | MMBtu | $3.01 |
TOTAL ENERGY COSTS | $24,243 | |||
RECOMMENDED SAVINGS* | $4,802 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,858 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $169 Cost: $100 |
$169 | 2,931 | - | - |
$169 2,931 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2711 UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING |
Savings: $1,267 Cost: $1,200 |
- | - | $1,267 | 421 |
- - kWh |
$1,267 421 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $992 Cost: - |
$199 | 3,224 | $793 | 263 |
$199 3,224 kWh |
$793 263 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $685 Cost: $2,076 |
$685 | 11,430 | - | - |
$685 11,430 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $1,689 Cost: $3,748 |
- | - | $1,689 | 561 |
- - kWh |
$1,689 561 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $4,802 Cost: $7,124 |
$1,053 | 17,585 | $3,749 | 1,245 | $1,053 17,585 kWh |
$3,749 1,245 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,858 Cost: $3,848 |
$169 | 2,931 | $1,689 | 561 | $169 2,931 kWh |
$1,689 561 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |