Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Univ. of Kansas |
---|---|
Assessment Year | 1983 |
Principal Product | FLUORESCENT LIGHT FIXTURES |
NAICS | n/a |
SIC | 3645 - Residential Lighting Fixtures |
Sales | $5,000,000-$10,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 450,000 Pieces |
Production Hrs. Annual | 4,572 |
Location (State) | KS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $53,764 | 715,123 | kWh | $0.08 |
Natural Gas | $46,392 | 9,495 | MMBtu | $4.89 |
TOTAL ENERGY COSTS | $100,156 | |||
RECOMMENDED SAVINGS* | $41,881 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,017 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2443 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR |
Savings: $12,636 Cost: $13,000 |
- | - | $12,636 | 2,584 |
- - kWh |
$12,636 2,584 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2443 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR |
Savings: $10,812 Cost: $8,500 |
- | - | $10,812 | 2,211 |
- - kWh |
$10,812 2,211 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,389 Cost: $4,629 |
$6,389 | 84,994 | - | - |
$6,389 84,994 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,608 Cost: $132 |
$3,608 | 48,066 | - | - |
$3,608 48,066 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4324 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT |
Savings: $2,533 Cost: $2,500 |
$2,533 | 33,705 | - | - |
$2,533 33,705 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $1,494 Cost: $2,800 |
$1,494 | - | - | - |
$1,494 - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $727 Cost: $200 |
$727 | 9,672 | - | - |
$727 9,672 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,237 Cost: $410 |
- | - | $1,237 | 253 |
- - kWh |
$1,237 253 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.1123 INSTALL AUTOMATIC STACK DAMPER |
Savings: $1,110 Cost: $2,589 |
- | - | $1,110 | 227 |
- - kWh |
$1,110 227 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $983 Cost: $192 |
- | - | $983 | 201 |
- - kWh |
$983 201 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $352 Cost: $100 |
$352 | 4,689 | - | - |
$352 4,689 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $41,881 Cost: $35,052 |
$15,103 | 181,126 | $26,778 | 5,476 | $15,103 181,126 kWh |
$26,778 5,476 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,017 Cost: $3,623 |
$4,687 | 62,427 | $3,330 | 681 | $4,687 62,427 kWh |
$3,330 681 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |