IAC Assessment: KU0134
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: KU0134
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Univ. of Kansas
Assessment Year 1984
Principal Product CORRUG SHIPPING CONTAINERS
NAICS n/a
SIC 2653 - Corrugated And Solid Fiber Boxes
Sales $10,000,000-$50,000,000
# of Employees 100
Plant Area (Sq.Ft.) 0
Annual Production 24,000 Tons
Production Hrs. Annual 6,024
Location (State) KS
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $191,767 2,985,053 kWh $0.06
Natural Gas $157,419 37,511 MMBtu $4.20
Other Energy $18,967 8,033 MMBtu $2.36
TOTAL ENERGY COSTS $368,153
RECOMMENDED SAVINGS* $113,412 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $36,888
#|Description Savings
Cost
Status Electricity Usage Natural Gas Other Energy Electricity Usage Natural Gas Other Energy
$ kWh $ MMBtu $ MMBtu
01: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$22,362
Cost:
$30,000
$18,435 286,928 $3,927 935 - - $18,435
286,928
kWh
$3,927
935
MMBtu
-
-
MMBtu
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$24,178
Cost:
$22,400
$24,178 376,319 - - - - $24,178
376,319
kWh
-
-
MMBtu
-
-
MMBtu
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$11,241
Cost:
$3,991
$11,241 174,971 - - - - $11,241
174,971
kWh
-
-
MMBtu
-
-
MMBtu
04: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS Savings:
$9,694
Cost:
$3,800
- - $9,694 2,308 - - -
-
kWh
$9,694
2,308
MMBtu
-
-
MMBtu
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$9,505
Cost:
$986
- - $9,505 2,263 - - -
-
kWh
$9,505
2,263
MMBtu
-
-
MMBtu
06: 2.1222 INSTALL TURBULATORS Savings:
$3,913
Cost:
$700
- - $3,913 932 - - -
-
kWh
$3,913
932
MMBtu
-
-
MMBtu
07: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS Savings:
$2,701
Cost:
-
- - $2,701 643 - - -
-
kWh
$2,701
643
MMBtu
-
-
MMBtu
08: 2.1123 INSTALL AUTOMATIC STACK DAMPER Savings:
$1,739
Cost:
$3,900
- - $1,739 414 - - -
-
kWh
$1,739
414
MMBtu
-
-
MMBtu
09: 2.1243 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER Savings:
$1,941
Cost:
$5,000
- - $1,941 462 - - -
-
kWh
$1,941
462
MMBtu
-
-
MMBtu
10: 2.2163 USE MINIMUM STEAM OPERATING PRESSURE Savings:
$1,264
Cost:
-
- - $1,264 301 - - -
-
kWh
$1,264
301
MMBtu
-
-
MMBtu
11: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC Savings:
$1,273
Cost:
$1,069
- - $1,273 303 - - -
-
kWh
$1,273
303
MMBtu
-
-
MMBtu
12: 2.1242 MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT Savings:
$457
Cost:
-
- - $457 109 - - -
-
kWh
$457
109
MMBtu
-
-
MMBtu
13: 2.2511 INSULATE BARE EQUIPMENT Savings:
$328
Cost:
$217
- - $328 78 - - -
-
kWh
$328
78
MMBtu
-
-
MMBtu
14: 2.4312 IMPROVE LUBRICATION PRACTICES Savings:
$7,532
Cost:
$3,000
$7,532 117,233 - - - - $7,532
117,233
kWh
-
-
MMBtu
-
-
MMBtu
15: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,352
Cost:
-
$3,352 52,169 - - - - $3,352
52,169
kWh
-
-
MMBtu
-
-
MMBtu
16: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$2,474
Cost:
$350
- - $2,474 589 - - -
-
kWh
$2,474
589
MMBtu
-
-
MMBtu
17: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$885
Cost:
$680
$885 13,775 - - - - $885
13,775
kWh
-
-
MMBtu
-
-
MMBtu
18: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$3,284
Cost:
$6,000
- - $3,284 782 - - -
-
kWh
$3,284
782
MMBtu
-
-
MMBtu
19: 2.2511 INSULATE BARE EQUIPMENT Savings:
$2,213
Cost:
$550
- - $2,213 527 - - -
-
kWh
$2,213
527
MMBtu
-
-
MMBtu
20: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,264
Cost:
$241
$508 7,913 $756 180 - - $508
7,913
kWh
$756
180
MMBtu
-
-
MMBtu
21: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$569
Cost:
-
- - - - $569 91 -
-
kWh
-
-
MMBtu
$569
91
MMBtu
22: 2.2511 INSULATE BARE EQUIPMENT Savings:
$508
Cost:
$60
$508 7,913 - - - - $508
7,913
kWh
-
-
MMBtu
-
-
MMBtu
23: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED Savings:
$395
Cost:
$250
$395 6,155 - - - - $395
6,155
kWh
-
-
MMBtu
-
-
MMBtu
24: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$340
Cost:
$41
- - $340 81 - - -
-
kWh
$340
81
MMBtu
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$113,412
Cost:
$83,235
$67,034 1,043,376 $45,809 10,907 $569 91 $67,034
1,043,376
kWh
$45,809
10,907
MMBtu
$569
91
MMBtu
TOTAL IMPLEMENTED Savings:
$36,888
Cost:
$9,027
$14,988 233,295 $21,900 5,214 - - $14,988
233,295
kWh
$21,900
5,214
MMBtu
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu $ MMBtu
Electricity Usage Natural Gas Other Energy Electricity Usage Natural Gas Other Energy