Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Univ. of Kansas |
---|---|
Assessment Year | 1985 |
Principal Product | SAFETY EQUIPMENT |
NAICS | n/a |
SIC | 3851 - Ophthalmic Goods |
Sales | $10,000,000-$50,000,000 |
# of Employees | 192 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 1,500,000 Pieces |
Production Hrs. Annual | 6,048 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $116,003 | 1,621,043 | kWh | $0.07 |
Natural Gas | $31,040 | 6,248 | MMBtu | $4.97 |
TOTAL ENERGY COSTS | $147,043 | |||
RECOMMENDED SAVINGS* | $35,708 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $34,367 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $10,215 Cost: $10,000 |
$5,305 | 74,150 | $4,910 | 988 | - | - |
$5,305 74,150 kWh |
$4,910 988 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $5,507 Cost: $1,300 |
$6,585 | 92,028 | $(-1,078) | (-217) | - | - |
$6,585 92,028 kWh |
$(-1,078) (-217) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,131 Cost: $5,120 |
$4,131 | 57,737 | - | - | - | - |
$4,131 57,737 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $2,055 Cost: - |
$2,055 | 28,722 | - | - | - | - |
$2,055 28,722 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7444 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS |
Savings: $1,363 Cost: $200 |
$1,363 | 19,050 | - | - | - | - |
$1,363 19,050 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $3,250 Cost: $2,500 |
$3,250 | 45,428 | - | - | - | - |
$3,250 45,428 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4312 IMPROVE LUBRICATION PRACTICES |
Savings: $610 Cost: - |
$1,384 | 19,343 | - | - | $(-774) | - |
$1,384 19,343 kWh |
- - MMBtu |
$(-774) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2514 COVER OPEN TANKS |
Savings: $3,927 Cost: $600 |
$4,613 | 64,478 | $(-686) | (-138) | - | - |
$4,613 64,478 kWh |
$(-686) (-138) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2212 USE MINIMUM SAFE OVEN VENTILATION |
Savings: $1,573 Cost: $2,800 |
$1,573 | 21,981 | - | - | - | - |
$1,573 21,981 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7229 AIR CONDITION ONLY SPACE NECESSARY |
Savings: $517 Cost: $1,060 |
- | - | $517 | 104 | - | - |
- - kWh |
$517 104 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.1123 INSTALL AUTOMATIC STACK DAMPER |
Savings: $636 Cost: $1,000 |
- | - | $636 | 128 | - | - |
- - kWh |
$636 128 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $461 Cost: $100 |
$461 | 6,448 | - | - | - | - |
$461 6,448 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $586 Cost: $175 |
- | - | $586 | 118 | - | - |
- - kWh |
$586 118 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $294 Cost: $43 |
$294 | 4,103 | - | - | - | - |
$294 4,103 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
15: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $105 Cost: $50 |
$105 | 1,465 | - | - | - | - |
$105 1,465 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
16: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $244 Cost: $35 |
$294 | 4,103 | $(-50) | (-10) | - | - |
$294 4,103 kWh |
$(-50) (-10) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
17: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $234 Cost: $43 |
- | - | $234 | 47 | - | - |
- - kWh |
$234 47 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $35,708 Cost: $25,026 |
$31,413 | 439,036 | $5,069 | 1,020 | $(-774) | - | $31,413 439,036 kWh |
$5,069 1,020 MMBtu |
$(-774) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $34,367 Cost: $23,891 |
$30,658 | 428,485 | $4,483 | 902 | $(-774) | - | $30,658 428,485 kWh |
$4,483 902 MMBtu |
$(-774) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |