Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Univ. of Kansas |
---|---|
Assessment Year | 1986 |
Principal Product | ACOUSTIC PANELS |
NAICS | n/a |
SIC | 3442 - Metal Doors, Sash, And Trim |
Sales | $5,000,000-$10,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 218,000 Pieces |
Production Hrs. Annual | 2,210 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $45,327 | 449,004 | kWh | $0.10 |
Natural Gas | $19,571 | 4,207 | MMBtu | $4.65 |
TOTAL ENERGY COSTS | $64,898 | |||
RECOMMENDED SAVINGS* | $11,630 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $10,377 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,876 Cost: $5,003 |
$3,876 | 38,394 | - | - | - | - |
$3,876 38,394 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $769 Cost: $100 |
$769 | 7,620 | - | - | - | - |
$769 7,620 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $4,524 Cost: $667 |
- | - | $4,524 | 973 | - | - |
- - kWh |
$4,524 973 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $273 Cost: - |
- | - | $423 | 91 | $(-150) | - |
- - kWh |
$423 91 MMBtu |
$(-150) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1123 INSTALL AUTOMATIC STACK DAMPER |
Savings: $1,097 Cost: $500 |
- | - | $1,097 | 236 | - | - |
- - kWh |
$1,097 236 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $802 Cost: $52 |
$207 | 2,052 | $595 | 128 | - | - |
$207 2,052 kWh |
$595 128 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $178 Cost: $75 |
$178 | 1,758 | - | - | - | - |
$178 1,758 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED |
Savings: $111 Cost: - |
- | - | $111 | 24 | - | - |
- - kWh |
$111 24 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $11,630 Cost: $6,397 |
$5,030 | 49,824 | $6,750 | 1,452 | $(-150) | - | $5,030 49,824 kWh |
$6,750 1,452 MMBtu |
$(-150) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $10,377 Cost: $6,270 |
$4,645 | 46,014 | $5,732 | 1,233 | - | - | $4,645 46,014 kWh |
$5,732 1,233 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |