IAC Assessment: KU0231
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: KU0231
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Univ. of Kansas
Assessment Year 1987
Principal Product GASKET DIE CUTS
NAICS n/a
SIC 3053 - Gaskets, Packing And Sealing Devices
Sales $5,000,000-$10,000,000
# of Employees 75
Plant Area (Sq.Ft.) 0
Annual Production 65,000,000 Pieces
Production Hrs. Annual 2,125
Location (State) MO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $31,629 350,234 kWh $0.09
Natural Gas $6,679 1,438 MMBtu $4.64
TOTAL ENERGY COSTS $38,308
RECOMMENDED SAVINGS* $7,554 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $2,424
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,553
Cost:
$2,059
$4,553 50,410 - - - - $4,553
50,410
kWh
-
-
MMBtu
-
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$847
Cost:
$100
$847 9,379 - - - - $847
9,379
kWh
-
-
MMBtu
-
-
$
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$809
Cost:
$40
$159 1,758 $650 140 - - $159
1,758
kWh
$650
140
MMBtu
-
-
$
04: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$445
Cost:
$600
$556 6,155 $(-111) (-24) - - $556
6,155
kWh
$(-111)
(-24)
MMBtu
-
-
$
05: 2.4312 IMPROVE LUBRICATION PRACTICES Savings:
$424
Cost:
$600
$424 4,689 - - - - $424
4,689
kWh
-
-
MMBtu
-
-
$
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$212
Cost:
$120
$212 2,345 - - - - $212
2,345
kWh
-
-
MMBtu
-
-
$
07: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED Savings:
$211
Cost:
-
$164 1,758 $47 10 - - $164
1,758
kWh
$47
10
MMBtu
-
-
$
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$132
Cost:
$250
$132 1,465 - - - - $132
1,465
kWh
-
-
MMBtu
-
-
$
09: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$(-79)
Cost:
-
- - $121 26 $(-200) - -
-
kWh
$121
26
MMBtu
$(-200)
-
$
TOTAL RECOMMENDED Savings:
$7,554
Cost:
$3,769
$7,047 77,959 $707 152 $(-200) - $7,047
77,959
kWh
$707
152
MMBtu
$(-200)
-
$
TOTAL IMPLEMENTED Savings:
$2,424
Cost:
$860
$1,806 19,929 $818 176 $(-200) - $1,806
19,929
kWh
$818
176
MMBtu
$(-200)
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes