IAC Assessment: KU0442
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: KU0442
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Univ. of Kansas
Assessment Year 1994
Principal Product Commercial lawnmowers
NAICS n/a
SIC 3523 - Farm Machinery And Equipment
Sales $10,000,000-$50,000,000
# of Employees 96
Plant Area (Sq.Ft.) 87,000
Annual Production 9,000 Pieces
Production Hrs. Annual 2,184
Location (State) NE
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $47,387 818,875 kWh $0.06
Natural Gas $36,128 9,280 MMBtu $3.89
TOTAL ENERGY COSTS $83,515
RECOMMENDED SAVINGS* $17,571 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $8,108
#|Description Savings
Cost
Status Electricity Usage Natural Gas Personnel Changes Primary Raw Material Electricity Usage Natural Gas Personnel Changes Primary Raw Material
$ kWh $ MMBtu $ $ $ $
01: 2.7145 INSTALL SKYLIGHTS Savings:
$7,072
Cost:
$35,400
$7,072 122,216 - - - - - - $7,072
122,216
kWh
-
-
MMBtu
-
-
$
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,001
Cost:
$8,058
$2,001 34,584 - - - - - - $2,001
34,584
kWh
-
-
MMBtu
-
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,523
Cost:
$4,449
$865 14,947 - - $658 - - - $865
14,947
kWh
-
-
MMBtu
$658
-
$
-
-
$
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$390
Cost:
$900
$390 6,741 - - - - - - $390
6,741
kWh
-
-
MMBtu
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$381
Cost:
$360
$153 2,638 - - $228 - - - $153
2,638
kWh
-
-
MMBtu
$228
-
$
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$179
Cost:
$325
$102 1,758 - - - - $77 - $102
1,758
kWh
-
-
MMBtu
-
-
$
$77
-
$
07: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$2,066
Cost:
$9,950
- - $2,066 531 - - - - -
-
kWh
$2,066
531
MMBtu
-
-
$
-
-
$
08: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$2,058
Cost:
$2,075
- - $2,058 529 - - - - -
-
kWh
$2,058
529
MMBtu
-
-
$
-
-
$
09: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,195
Cost:
$8,640
$(-594) (-10,258) $1,789 460 - - - - $(-594)
(-10,258)
kWh
$1,789
460
MMBtu
-
-
$
-
-
$
10: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$435
Cost:
$400
$322 5,569 $113 29 - - - - $322
5,569
kWh
$113
29
MMBtu
-
-
$
-
-
$
11: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$271
Cost:
$130
$271 4,689 - - - - - - $271
4,689
kWh
-
-
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$17,571
Cost:
$70,687
$10,582 182,884 $6,026 1,549 $886 - $77 - $10,582
182,884
kWh
$6,026
1,549
MMBtu
$886
-
$
$77
-
$
TOTAL IMPLEMENTED Savings:
$8,108
Cost:
$26,329
$1,119 19,343 $6,026 1,549 $886 - $77 - $1,119
19,343
kWh
$6,026
1,549
MMBtu
$886
-
$
$77
-
$
Savings
Cost
$ kWh $ MMBtu $ $ $ $
Electricity Usage Natural Gas Personnel Changes Primary Raw Material Electricity Usage Natural Gas Personnel Changes Primary Raw Material