IAC Assessment: KU0468
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: KU0468
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Univ. of Kansas
Assessment Year 1996
Principal Product insulated wire, harnesses, magnetos
NAICS n/a
SIC 3714 - Motor Vehicle Parts And Accessories
Sales $5,000,000-$10,000,000
# of Employees 65
Plant Area (Sq.Ft.) 55,000
Annual Production 250,000 Pieces
Production Hrs. Annual 2,000
Location (State) MO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $46,210 805,686 kWh $0.06
Electricity Demand $10,314 3,456 kW-months/year $2.98
Natural Gas $10,366 2,511 MMBtu $4.13
TOTAL ENERGY COSTS $67,890
RECOMMENDED SAVINGS* $38,079 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $37,828
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Other Liquid (non-haz) Solid Waste (non-haz) Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Other Liquid (non-haz) Solid Waste (non-haz) Personnel Changes Primary Raw Material
$ kWh $ kW-months/year $ gal $ lb $ $ $ $
01: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS Savings:
$29,684
Cost:
$15,000
- - $(-1,046) (-348) - - $(-6,000) 80,000 $(-3,750) - $40,480 - -
-
kWh
$(-1,046)
(-348)
kW-months/year
-
-
gal
$(-6,000)
80,000
lb
$(-3,750)
-
$
$40,480
-
$
02: 3.4115 RECOVER AND REUSE COOLING WATER Savings:
$4,610
Cost:
$8,000
$(-1,144) (-19,930) $(-358) (-120) $6,112 1,184,000 - - - - - - $(-1,144)
(-19,930)
kWh
$(-358)
(-120)
kW-months/year
$6,112
1,184,000
gal
-
-
lb
-
-
$
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,860
Cost:
$191
$1,502 26,377 $358 120 - - - - - - - - $1,502
26,377
kWh
$358
120
kW-months/year
-
-
gal
-
-
lb
-
-
$
-
-
$
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$582
Cost:
$700
$450 7,913 $132 48 - - - - - - - - $450
7,913
kWh
$132
48
kW-months/year
-
-
gal
-
-
lb
-
-
$
-
-
$
05: 2.2511 INSULATE BARE EQUIPMENT Savings:
$566
Cost:
$444
$432 7,620 $134 48 - - - - - - - - $432
7,620
kWh
$134
48
kW-months/year
-
-
gal
-
-
lb
-
-
$
-
-
$
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$526
Cost:
$137
$425 7,327 $101 26 - - - - - - - - $425
7,327
kWh
$101
26
kW-months/year
-
-
gal
-
-
lb
-
-
$
-
-
$
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$251
Cost:
$360
$114 2,052 $137 48 - - - - - - - - $114
2,052
kWh
$137
48
kW-months/year
-
-
gal
-
-
lb
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$38,079
Cost:
$24,832
$1,779 31,359 $(-542) (-178) $6,112 1,184,000 $(-6,000) 80,000 $(-3,750) - $40,480 - $1,779
31,359
kWh
$(-542)
(-178)
kW-months/year
$6,112
1,184,000
gal
$(-6,000)
80,000
lb
$(-3,750)
-
$
$40,480
-
$
TOTAL IMPLEMENTED Savings:
$37,828
Cost:
$24,472
$1,665 29,307 $(-679) (-226) $6,112 1,184,000 $(-6,000) 80,000 $(-3,750) - $40,480 - $1,665
29,307
kWh
$(-679)
(-226)
kW-months/year
$6,112
1,184,000
gal
$(-6,000)
80,000
lb
$(-3,750)
-
$
$40,480
-
$
Savings
Cost
$ kWh $ kW-months/year $ gal $ lb $ $ $ $
Electricity Usage Electricity Demand Other Liquid (non-haz) Solid Waste (non-haz) Personnel Changes Primary Raw Material Electricity Usage Electricity Demand Other Liquid (non-haz) Solid Waste (non-haz) Personnel Changes Primary Raw Material