Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Univ. of Kansas |
---|---|
Assessment Year | 1997 |
Principal Product | heating elements |
NAICS | n/a |
SIC | 3567 - Industrial Furnaces And Ovens |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 44,000 |
Annual Production | 535,000 Pieces |
Production Hrs. Annual | 4,318 |
Location (State) | KS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $49,702 | 1,230,070 | kWh | $0.04 |
Electricity Demand | $27,783 | 6,708 | kW-months/year | $4.14 |
Natural Gas | $8,625 | 1,379 | MMBtu | $6.25 |
TOTAL ENERGY COSTS | $101,811 | |||
RECOMMENDED SAVINGS* | $34,080 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $26,850 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $13,340 Cost: - |
$19,620 | 497,069 | $10,730 | 2,592 | $(-17,010) | (-2,898) | - | - | - | - | - | - |
$19,620 497,069 kWh |
$10,730 2,592 kW-months/year |
$(-17,010) (-2,898) MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $1,540 Cost: $5,580 |
- | - | - | - | $1,540 | 263 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,540 263 MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,360 Cost: $5,470 |
$980 | 24,619 | $380 | 92 | - | - | - | - | - | - | - | - |
$980 24,619 kWh |
$380 92 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,010 Cost: $230 |
$780 | 19,930 | $230 | 55 | - | - | - | - | - | - | - | - |
$780 19,930 kWh |
$230 55 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $780 Cost: $1,400 |
$780 | 19,930 | - | - | - | - | - | - | - | - | - | - |
$780 19,930 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $490 Cost: $780 |
$170 | 4,396 | $20 | 6 | - | - | - | - | $300 | - | - | - |
$170 4,396 kWh |
$20 6 kW-months/year |
- - MMBtu |
- - lb |
$300 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $370 Cost: $810 |
$750 | 19,050 | $90 | 21 | $(-470) | (-81) | - | - | - | - | - | - |
$750 19,050 kWh |
$90 21 kW-months/year |
$(-470) (-81) MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $180 Cost: $270 |
$140 | 3,517 | $40 | 9 | - | - | - | - | - | - | - | - |
$140 3,517 kWh |
$40 9 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.5221 RECYCLE CASTING SAND |
Savings: $4,050 Cost: - |
- | - | - | - | - | - | $4,050 | 180,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$4,050 180,000 lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS |
Savings: $3,340 Cost: $300 |
- | - | - | - | - | - | - | 250 | - | - | $3,340 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- 250 lb |
- - $ |
$3,340 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 4.122 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS |
Savings: $7,620 Cost: - |
- | - | - | - | - | - | - | - | $7,620 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$7,620 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $34,080 Cost: $14,840 |
$23,220 | 588,511 | $11,490 | 2,775 | $(-15,940) | (-2,716) | $4,050 | 180,250 | $7,920 | - | $3,340 | - | $23,220 588,511 kWh |
$11,490 2,775 kW-months/year |
$(-15,940) (-2,716) MMBtu |
$4,050 180,250 lb |
$7,920 - $ |
$3,340 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $26,850 Cost: $6,270 |
$21,520 | 545,135 | $11,380 | 2,748 | $(-17,010) | (-2,898) | - | 250 | $7,620 | - | $3,340 | - | $21,520 545,135 kWh |
$11,380 2,748 kW-months/year |
$(-17,010) (-2,898) MMBtu |
- 250 lb |
$7,620 - $ |
$3,340 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material |