IAC Assessment: KU0502
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: KU0502
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Univ. of Kansas
Assessment Year 1998
Principal Product Custom thermoplastic parts
NAICS n/a
SIC 3089 - Plastics Products, Nec
Sales $5,000,000-$10,000,000
# of Employees 90
Plant Area (Sq.Ft.) 33,200
Annual Production 40,000,000 Pieces
Production Hrs. Annual 8,256
Location (State) KS
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $72,037 3,186,401 kWh $0.02
Electricity Demand $41,975 7,920 kW-months/year $5.30
Natural Gas $965 163 MMBtu $5.92
TOTAL ENERGY COSTS $138,080
RECOMMENDED SAVINGS* $132,830 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $131,990
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Solid Waste (non-haz) Administrative Changes Primary Raw Material Ancillary Material Cost Primary Product Electricity Usage Electricity Demand Electricity Fees Solid Waste (non-haz) Administrative Changes Primary Raw Material Ancillary Material Cost Primary Product
$ kWh $ kW-months/year $ $ $ lb $ $ $ $ $ $ $ $
01: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$7,420
Cost:
$12,600
- - $5,980 - $1,440 - - - - - - - - - - - -
-
kWh
$5,980
-
kW-months/year
$1,440
-
$
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$840
Cost:
$2,170
$630 27,843 $210 40 - - - - - - - - - - - - $630
27,843
kWh
$210
40
kW-months/year
-
-
$
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$280
Cost:
$330
$210 9,379 $70 14 - - - - - - - - - - - - $210
9,379
kWh
$70
14
kW-months/year
-
-
$
-
-
lb
-
-
$
-
-
$
-
-
$
-
-
$
04: 2.4314 USE SYNTHETIC LUBRICANT Savings:
$210
Cost:
$300
$140 6,155 $50 9 - - - - - - $20 - - - - - $140
6,155
kWh
$50
9
kW-months/year
-
-
$
-
-
lb
-
-
$
$20
-
$
-
-
$
-
-
$
05: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$2,070
Cost:
$7,680
- - - - - - $2,170 102,000 - - - - $(-100) - - - -
-
kWh
-
-
kW-months/year
-
-
$
$2,170
102,000
lb
-
-
$
-
-
$
$(-100)
-
$
-
-
$
06: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$1,380
Cost:
-
- - - - - - - - $1,380 - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
lb
$1,380
-
$
-
-
$
-
-
$
-
-
$
07: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$83,890
Cost:
$42,990
$(-9,760) (-431,712) $(-13,420) (-2,532) - - - - $107,070 - - - - - - - $(-9,760)
(-431,712)
kWh
$(-13,420)
(-2,532)
kW-months/year
-
-
$
-
-
lb
$107,070
-
$
-
-
$
-
-
$
-
-
$
08: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY Savings:
$36,740
Cost:
$4,590
- - - - - - - - - - $12,390 - - - $24,350 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
lb
-
-
$
$12,390
-
$
-
-
$
$24,350
-
$
TOTAL RECOMMENDED Savings:
$132,830
Cost:
$70,660
$(-8,780) (-388,335) $(-7,110) (-2,469) $1,440 - $2,170 102,000 $108,450 - $12,410 - $(-100) - $24,350 - $(-8,780)
(-388,335)
kWh
$(-7,110)
(-2,469)
kW-months/year
$1,440
-
$
$2,170
102,000
lb
$108,450
-
$
$12,410
-
$
$(-100)
-
$
$24,350
-
$
TOTAL IMPLEMENTED Savings:
$131,990
Cost:
$68,490
$(-9,410) (-416,178) $(-7,320) (-2,509) $1,440 - $2,170 102,000 $108,450 - $12,410 - $(-100) - $24,350 - $(-9,410)
(-416,178)
kWh
$(-7,320)
(-2,509)
kW-months/year
$1,440
-
$
$2,170
102,000
lb
$108,450
-
$
$12,410
-
$
$(-100)
-
$
$24,350
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ lb $ $ $ $ $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Solid Waste (non-haz) Administrative Changes Primary Raw Material Ancillary Material Cost Primary Product Electricity Usage Electricity Demand Electricity Fees Solid Waste (non-haz) Administrative Changes Primary Raw Material Ancillary Material Cost Primary Product