IAC Assessment: KU0537
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: KU0537
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Univ. of Kansas
Assessment Year 2000
Principal Product fossil fuel burners
NAICS n/a
SIC 3433 - Heating Equipment, Except Electric
Sales $10,000,000-$50,000,000
# of Employees 220
Plant Area (Sq.Ft.) 149,000
Annual Production 6,016 Pieces
Production Hrs. Annual 4,080
Location (State) KS
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $84,778 2,032,532 kWh $0.04
Electricity Demand $23,677 6,607 kW-months/year $3.58
Natural Gas $22,121 4,100 MMBtu $5.40
TOTAL ENERGY COSTS $125,224
RECOMMENDED SAVINGS* $6,110 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Water Consumption Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Water Consumption
$ kWh $ kW-months/year $ $ $ $ $ Tgal
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$970
Cost:
$1,480
$760 18,757 $50 16 $160 - - - - - $760
18,757
kWh
$50
16
kW-months/year
$160
-
$
-
-
$
-
-
Tgal
02: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$580
Cost:
-
$580 14,361 - - - - - - - - $580
14,361
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
Tgal
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$400
Cost:
$200
$320 7,913 $80 23 - - - - - - $320
7,913
kWh
$80
23
kW-months/year
-
-
$
-
-
$
-
-
Tgal
04: 3.4155 METER WASTE WATER Savings:
$2,980
Cost:
$1,910
- - - - - - $2,980 - - - -
-
kWh
-
-
kW-months/year
-
-
$
$2,980
-
$
-
-
Tgal
05: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION Savings:
$1,180
Cost:
$1,740
- - - - - - - - $1,180 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
$1,180
-
Tgal
TOTAL RECOMMENDED Savings:
$6,110
Cost:
$5,330
$1,660 41,031 $130 39 $160 - $2,980 - $1,180 - $1,660
41,031
kWh
$130
39
kW-months/year
$160
-
$
$2,980
-
$
$1,180
-
Tgal
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ Tgal
Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Water Consumption Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Water Consumption